The Client wants to use or take over part of the works before Completion

What a Contractor should do when the Client wants to use or take over part of the works early: defects, damage, insurance and the programme.

Defects, quality and completionScenario4 min read

On this page
  1. The short answer
  2. What to do, step by step
  3. What to record
  4. What not to do
  5. When to get help
  6. Related guides

The Client has said they want to start using, or take over, part of the works before the whole job is complete. It might be a section that is ready to operate, or an area they want to fit out. This guide is written for the Contractor. A Subcontractor will face the same question from the Contractor, and the same points apply.

The short answer

Do not agree informally. Early use or take over can change risk, insurance, defects periods, access, programme and cost, and you need all of these dealt with in writing first. Ask the Project Manager for an instruction in the form your contract requires, and check what your contract says about take over before Completion, because the rules differ between versions and Z clauses.

What to do, step by step

  1. Find out what is being asked. Is the Client asking to take over a defined part of the works, or just to use or access it? These are different things under the contract. Ask for a description of the area, the date and the purpose.
  2. Read the contract. Look at the clauses on Completion, take over and the Client's use of the works. Under clause 35.2, if the Client uses a part of the works before Completion, that part is treated as taken over, unless the Scope gives a reason for the use or the use suits the Contractor's way of working. So a Client who simply moves in has probably taken over that part, whether or not anyone planned it. Check Z clauses and the Contract Data.
  3. Ask for it in writing. Use the communication system under clause 13. Ask the Project Manager to confirm the request and to state whether it is an instruction.
  4. Assess the effect on the programme. Which activities are affected? Does access to the rest of the works get harder? Does the remaining work have to be resequenced or done in a different way? If you need help, see Key Dates and sectional Completion.
  5. Check the compensation event position. If the request leads to extra cost or delay, look at the compensation event list in clause 60.1 and decide whether to notify. Take over of a part before both Completion and the Completion Date is a compensation event under 60.1(15). The Project Manager has one week to certify the date and extent of the take over (35.3), and if no certificate comes, write and ask for it. Remember the eight-week limit in clause 61.3.
  6. Agree the practical points. Condition survey and photographs of the area, security, safety and welfare arrangements, who is responsible for operating and protecting it, and what remains outstanding.
  7. Check insurance and risk. Ask your insurance team to confirm cover. Loss of or damage to a part taken over generally becomes the Client's liability (clause 80.1), with exceptions such as a Defect that existed at take over or damage from the Contractor's own later work. Check the exact exceptions in your contract.
  8. Consider defects and delay damages. Under the standard wording, take over of a part does not start the Defects Date, which still counts from Completion of the whole of the works. Where the Client needs to give access for you to correct a Defect in the part taken over, the correction period starts once access and use are given (44.4 in NEC4, 43.4 in NEC3). If Option X7 applies, delay damages are reduced from the take over date in proportion to the benefit of the part taken over, as the Project Manager assesses, and they stop if the whole works are taken over. Retention under Option X16 is unaffected until the whole is taken over or complete. See Completion, take over and the Defects Date explained.
  9. Update the programme. Submit a revised programme if it is instructed or if the plan changes, using the process in clause 32.2.

What to record

  • The Client's request and every reply, with dates
  • The Project Manager's instruction, if one is given
  • A dated photographic and written record of the area at the point of use or take over
  • Who was on site and what they did in that area
  • Any damage found afterwards, and when it was noticed
  • The effect on the programme and on cost, as it unfolds

What not to do

  • Do not let the Client in verbally and sort it out later.
  • Do not assume the programme can absorb it with no cost.
  • Do not hand over keys, access or utilities without a note of the condition.
  • Do not forget the Subcontractors working in that area. Their programme and safety arrangements are affected too.
  • Do not assume Completion has happened for the part. Take over is not Completion: the Completion test still applies to the works, or to a section if Option X5 is used.

When to get help

Involve your commercial manager at the first request, since money and risk are involved. Bring in a planner when the access or sequence changes, so the effect can be shown in a programme. Take legal advice if the Client wants to take over against your objection.

This guide is general information, not legal advice. Check it against your contract.