A planner who can drive Primavera P6 is not the same as a planner who can run a programme under an NEC contract. The first builds a schedule. The second builds one that survives acceptance, supports compensation events and stands up if the project goes wrong. Hiring for the wrong skill is a common and costly mistake.

What to look for

P6 skills

  • Fluent in building logic-driven schedules, not just drawing bars
  • Comfortable with calendars, resources, baselines and global changes
  • Able to run schedule quality checks and explain the results
  • Able to produce clean exports and reports to a client's format

NEC skills

  • Knows what clause 31.2 requires and builds it in from the start
  • Has prepared compensation event programmes and quotations
  • Understands the Accepted Programme and how it drives time assessment
  • Writes clear programme narratives and schedules of changes
  • Is comfortable with early warnings and the eight-week notification period for compensation events

Sector knowledge

  • Water and wastewater, utilities, tunnelling, highways, rail and energy all have their own possessions, permits, shutdown windows and client requirements. Experience in your sector shortens the learning curve.

Questions worth asking

  1. "Talk me through what you include in a first programme under clause 31.2."
  2. "How do you deal with negative float in a revised programme?"
  3. "What would you do if a Project Manager rejects the programme?"
  4. "How do you show time risk allowance, and where do you put it?"
  5. "Tell me about a compensation event programme you prepared and how it was received."
  6. "How do you check the quality of a schedule before you issue it?"

A strong planner answers with examples. A weaker one gives definitions.

Red flags

  • Cannot explain the difference between float and time risk allowance
  • Uses lags and constraints to force dates
  • Has never worked under NEC, or only on one Option
  • Cannot show sample outputs (with client details removed)

Permanent hire or contract cover?

Situation Often best
Steady, long-term programme load Permanent hire
Peak workload or a tender period Contract planner
Single project with a defined duration Contract planner
Programme in trouble, needs fixing fast Experienced contract planner
Short-term cover for leave or sickness Contract planner

Contract cover lets you buy exactly the days you need. It also means you can bring in specialist NEC experience without carrying it year-round.

How CPMP can help

CPMP Network supplies experienced P6 and NEC planners to contractors, for days, weeks or months. Tell us about the project, the contract and the skills you need, and we will match a planner who has done it before.

This guide is general information, not legal advice. Check it against your contract.