A Contract Data checklist for contractors before signing an NEC contract

The Contract Data entries a contractor should check before signing an NEC contract, from periods and Key Dates to Options and retention.

Tendering and starting a contract5 min read

On this page
  1. Start with the version and the Z clauses
  2. Checklist
  3. Questions to ask
  4. Common traps
  5. What to do with problems
  6. Related guides

The Contract Data is where an NEC contract becomes your contract. The core clauses are standard, but the periods, dates, percentages and choices in the Contract Data decide how much time you have, how often you must report and how much risk you carry. Check it line by line before you sign, because afterwards you are bound by what it says. This checklist is written for contractors. Subcontractors should check the equivalent entries in their subcontract.

Start with the version and the Z clauses

Confirm whether the contract is NEC3 or NEC4, and read every Z clause. Z clauses often change time bars, payment, programme and compensation event rules. See Z clauses: how to read the amendments.

Checklist

Item What to check
Main Option Which core Option applies (A to F)? Does your pricing method and risk allocation match it?
Secondary Options Check each one, in particular those on completion damages, retention, price adjustment and the dispute resolution Option
Starting date and access dates Do they match when you can really start and when the Client will give access?
Completion Date and Key Dates Are they achievable on your tender programme? Do any Key Dates depend on the Client's actions?
Sectional Completion If there are sections, check each date and the conditions. See Key Dates and sectional Completion
Programme submission The period for submitting the first programme, and whether part two of the Contract Data identifies a programme (in which case no first programme is due). Where none is identified, a quarter of the Price for Work Done to Date is held back until a first programme showing the required information has been submitted
Revised programme interval The longest interval between revised programmes, and whether you can resource that
Assessment interval How often the Project Manager assesses the amount due. Under NEC4 you must apply before each assessment date, and a missed application means the amount due cannot rise above the previous figure. Also check for a different payment period (the standard is three weeks from the assessment date)
Period for reply The time for replies to communications, and whether it fits how the Client's team works. A late reply by the Project Manager can be a compensation event, so the figure matters to both sides. Also check the early warning meeting interval (a NEC4 entry) and the place and data for weather measurement
Defects date The defects date and the defect correction periods, and who is liable for Defects found after Completion. Correcting Defects after Completion is Disallowed Cost on the cost-based Options
Delay damages Whether Option X7 is chosen, and the rate per day. Damages run from the Completion Date until the earlier of Completion and take over. Compare the rate with your own cost of delay
Retention If Option X16 is chosen, the retention free amount and percentage (applied to the value above the free amount), and whether a retention bond is allowed (NEC4). Without X16 there is no retention
Bond or guarantees Amounts, forms and who provides them
Insurance Levels of cover, what you must provide and what the Client provides
Limits on liability Any cap on the Contractor's liability and what it covers
Interest rate The rate applied to late payment, which runs daily and is compounded annually
Time-related items Any periods that differ from the standard ones. The eight weeks to notify a compensation event, the three weeks for a quotation and the two weeks for a reply to it sit in the core clauses, not the Contract Data, so a different figure will be in a Z clause
Scope and design Whether the Scope puts design on you, and whether you have the design information you priced

Questions to ask

  1. Can I build it by the dates? Compare Completion and Key Dates with your tender programme, including your realistic productivity, weather, consents and access.
  2. Does the programme submission period leave me enough time? If the first programme is due soon after the contract starts, you need the planning resource ready.
  3. Can I afford the reporting? Frequent revised programme intervals and early warning meetings take staff time. Check how many people that needs.
  4. What happens if I am late? Read the delay damages entry and the Option behind it. Work out your exposure for a delay of four weeks.
  5. When do I get paid? Work out the cash flow from the assessment interval, the payment period, retention and any other deductions. See How payment works under NEC.
  6. What is missing? Blank entries in the Contract Data can mean the contract default applies, or that something was never agreed. Ask which.
  7. Does everything flow down? If you will subcontract, make sure your subcontract dates, periods and Options leave you room before your own deadlines.

Common traps

  • Key Dates set for the Client's benefit but missing the Client's own dependencies
  • Delay damages set high with no cap on liability (Option X18 is the standard route to a cap)
  • Short reply periods in the Contract Data, or shortened quotation periods in a Z clause, that do not match how your team works
  • A programme submission date that falls before you have the information to produce one
  • A low retention free amount, or retention held until the end of a long defects stage
  • Differences between the tender documents and the Contract Data you are asked to sign

What to do with problems

Raise them in writing before signing, while you still have negotiating leverage. Once the contract is signed, the Contract Data is what you work to. If you cannot change an entry, at least price the risk and plan the response.

This guide is general information, not legal advice. Check it against your contract.