Compensation event quotation: template and guide

What a clause 62 compensation event quotation must contain, how to price time and money, and a template you can adapt.

Compensation events and change4 min read

On this page
  1. Before you quote
  2. What a quotation contains
  3. How time is assessed
  4. Timing
  5. Template
  6. Common mistakes

A compensation event (CE) quotation is the Contractor's priced and timed proposal for the effect of an event on the contract. Under clause 62 it covers changes to the Prices and any delay to the Completion Date and Key Dates, and it usually includes a revised programme where the event affects the remaining work. Read clauses 60 to 65 in your contract for the exact rules and time periods.

Before you quote

  1. Check the notification. The Contractor must notify a CE within eight weeks of becoming aware that it has happened (clause 61.3; seven weeks under the NEC4 subcontract). The bar does not apply to events arising from an instruction, notification, certificate or changed decision of the Project Manager or Supervisor, which the Project Manager should notify itself (61.1). Quoting on a late-notified event can fail on the time bar alone. Use our notice drafting tool.
  2. Wait for instruction. Once the Project Manager has decided that a notified event is a compensation event (it has one week to do so, 61.4), it instructs the Contractor to submit quotations, except where the event is the Contractor's fault or quotations have already been submitted. If the Project Manager does not decide in time, the Contractor can notify the failure, and two weeks later the event is treated as accepted with quotations instructed.
  3. Price on the right basis. Whatever the main Option, the assessment is the effect of the event on Defined Cost, actual up to the dividing date and forecast after it, plus the Fee (clause 63.1). It is not priced at tender or bill rates unless both sides agree rates or lump sums (63.2 in NEC4; Option clauses in NEC3). Your Option affects how the result flows through payment, not the basis of the quotation.

What a quotation contains

  • The cost effect: changes to the Prices, built up from the contract's pricing basis for your Option.
  • The time effect: the delay to the Completion Date and to any Key Date.
  • A revised programme if the event changes the plans for the remaining work, showing the effect on planned Completion.
  • The details of the assessment, so the Project Manager can check how the figures were reached.
  • Alternative quotations where the Project Manager has asked for them.

How time is assessed

Delay to the Completion Date is assessed by reference to the Accepted Programme. It is the length of time that, because of the event, planned Completion is later than planned Completion shown on the Accepted Programme, and the Completion Date moves by that amount. NEC4 uses the Accepted Programme in force at the dividing date (63.5); NEC3 refers simply to the Accepted Programme (63.3). The test is planned Completion, not the Completion Date, so float before planned Completion can absorb an event and the gap between planned Completion and the Completion Date (terminal float) is not used up. This is a forward-looking assessment of the remaining work, which is why a good, accepted programme matters so much. Read more in our delay analysis basics.

Timing

In the standard ECC the Contractor submits the quotation within three weeks of being instructed (62.3), and the Project Manager replies within two weeks of submission. The reply is an acceptance, an instruction to submit a revised quotation (due within three weeks), or a statement that the Project Manager will assess the event itself (NEC3 has a further reply for proposed instructions, which NEC4 moved to clause 65). Both sides can agree an extension, but only before the submission or reply is due (62.5). If the Contractor is late, the Project Manager can assess the event (64.1). If the Project Manager does not reply, the Contractor can notify the failure, and if there is still no reply two weeks later the quotation is treated as accepted (62.6). The NEC4 subcontract uses longer periods, and Z clauses often amend these, so check your Contract Data and diarise every date.

Template

Section What to write
Reference CE number and project reference
Event What happened, the date, and the clause 60.1 item relied on
Notification Date notified and the date the Contractor became aware
Scope of change What work is added, omitted or changed
Cost Build-up of Defined Cost (actual to the dividing date, forecast after it) and Fee, with risk allowances explained
Time Delay to Completion Date and each affected Key Date, in days
Programme Reference to the revised programme and the activities affected
Assumptions Any assumptions the Project Manager must confirm
Risks Risks the Contractor has and has not priced
Signed Name, role, date

Common mistakes

  • Quoting without a valid notification.
  • Pricing time-related costs without showing the delay on the programme.
  • Not updating the programme logic to show how the event actually affects the work.
  • Failing to show assumptions, which gives the Project Manager grounds to reject the quotation.

This guide is general information, not legal advice. Check it against your contract.