Early warning register template

How early warnings work under NEC, what to record in the register, and a template you can copy.

Early warning and risk3 min read

On this page
  1. Why it matters
  2. What triggers an early warning
  3. The early warning meeting
  4. Register template
  5. Tips for a register that works
  6. Common mistakes

Early warning is one of the core NEC principles. Under clause 15.1 in NEC4 (clause 16.1 in NEC3) the Contractor and the Project Manager must each give an early warning as soon as they become aware of any matter that could increase the total of the Prices, delay Completion, delay meeting a Key Date, or impair the performance of the works in use. The Contractor may also warn of anything else that could raise its own total cost. The Project Manager enters each matter in the Early Warning Register, and no warning is needed for something already notified as a compensation event. If the Contractor gives no early warning that an experienced contractor could have given, the Project Manager can say so when it instructs quotations (clause 61.5), and the related compensation event is then assessed as if the warning had been given (63.7 in NEC4, 63.5 in NEC3). The event is not lost, but its value may be lower.

NEC4 also puts the register on a timetable. The Project Manager issues the first Early Warning Register within one week of the starting date, and the first early warning meeting is held within two weeks of it. The Contract Data sets the longest gap between later meetings, and the Project Manager issues the revised register within one week of each meeting. NEC3 sets no fixed times. Check your Contract Data and Z clauses, because these periods can be amended.

Why it matters

  • It is a contractual duty, not a courtesy.
  • It starts the conversation about mitigation while there is still time to act.
  • It protects the Contractor: a Project Manager who was warned early is less able to say the Contractor should have avoided the problem.
  • A well-kept register gives a record of what was known, when, and what was agreed.

What triggers an early warning

Anything that could:

  1. Increase the total of the Prices
  2. Delay Completion
  3. Delay meeting a Key Date
  4. Impair the performance of the works in use

If in doubt, give the warning. A warning that turns out to be unnecessary costs little. A missing one can cost a lot.

The early warning meeting

Either party may instruct the other to attend a meeting, and others such as a designer or subcontractor can attend if the other side agrees. At the meeting the parties co-operate to make and consider proposals for avoiding or reducing the effect, seek solutions that will bring advantage to all those affected, and decide on actions and who will take them. NEC4 also has them review actions already recorded and change them if needed. The Project Manager updates the register to record the decisions, and instructs any change to the Scope that a decision needs, within one week of the meeting in NEC4 (clause 15.4). See clauses 15.2 to 15.4 (NEC4) or 16.2 to 16.4 (NEC3).

Register template

Copy this table into a spreadsheet and keep it live.

Ref Date raised Raised by Description Could affect Effect (cost / time / Key Date / quality) Proposed mitigation Action owner Due Status Meeting date Linked CE
EW-001 Open / Closed

Tips for a register that works

  • Number every entry and never delete one. Close it instead.
  • Record the date you became aware, not the date you wrote it up. You will need it for compensation event time bars.
  • Link each warning to a compensation event if one follows. Clause 61.3 gives the Contractor eight weeks from becoming aware of an event to notify it (seven weeks under the NEC4 subcontract). An early warning is not that notification.
  • Review the register at every progress meeting.
  • Be specific about the effect. "Delay possible" is weak. "Two-week delay to Key Date 2 if possession is not granted by 14 March" is useful.

Common mistakes

  • Waiting until the problem has happened. An early warning is about what could happen.
  • Giving a warning verbally only, with no written record.
  • Not following up with a meeting.
  • Letting the register go stale.

This guide is general information, not legal advice. Check it against your contract.