NEC early warning notice: wording you can copy
A ready-to-use early warning layout for NEC4 contracts with a filled-in example and notes on adapting it for NEC3, subcontracts and short forms.
Below is a layout you can paste into an email or letter. NEC does not set a form for early warnings, so first check whether your Scope (the document describing the work and how it must be done) names a system or format. If it does, use that. The wording here is our own sample, written for the NEC4 Engineering and Construction Contract.
The layout
Send it as its own communication, never buried in another message. Square brackets are for you to fill in.
Early warning notice, clause 15.1 Contract: [name and number] Reference: EW-[number] Date: [date issued] From / To: [name and role, Contractor or Project Manager] The matter: [what you have learned and what could result] Date we became aware: [date] It could affect: [keep what applies] the total of the Prices; Completion; a named Key Date; performance of the works in use; the Contractor's own total cost (optional warning) What we suggest: [one or two options to avoid or reduce the effect] What we need, and by when: [decision or information, from whom, latest useful date] Meeting: [add to the next meeting on (date)] or [please attend a meeting on (date, time, place)] Note: this is an early warning only. It is not notice of a compensation event and takes no view on responsibility.
A filled-in example
This is invented, with round figures.
- Contract: Riverside Culvert Replacement, RCR/031
- Reference: EW-017, Contractor's Site Manager to Project Manager
- The matter: Trial pits today show the existing headwall in worse condition than assumed. If it needs rebuilding rather than repairing, the planned road closure could run longer, which could conflict with the council's agreed reopening date.
- It could affect: Prices (range not yet known); Key Date 2, reopening, by several days.
- What we suggest: A structural inspection this week, and pre-ordering precast units to protect the closure.
- What we need: Confirmation by Thursday of whether the council can extend the closure.
- Meeting: Please attend a meeting on site on Friday at 09:00.
Notice what it avoids. It does not call the findings a compensation event, and it does not rule that out. If you later decide they are a physical condition (a listed event for ground conditions), you give a separate notice within the time limit for notifying events.
Adapting it
| Contract | Change |
|---|---|
| NEC3 ECC | Cite clause 16.1 and call the meeting a risk reduction meeting; the register is the Risk Register |
| NEC4 subcontract | Parties become Contractor and Subcontractor; either may give the optional cost warning |
| Short contracts | Drop the meeting line, as there are no formal meetings; ask to co-operate on a response |
| Professional service forms | Use that contract's own list of effects and role names |
Tips
- Do not hold the notice back to fill every field. "Not yet known" is a fair answer; update it at the meeting.
- Agree one numbering series with the other side at the start, so notices and the register line up.
- Only instruct attendance if you mean it. Either party can under clause 15.2, but delete the line if the next scheduled meeting is soon enough.
- Keep a copy with proof of delivery, so you can show later that you warned and when.
Related guides
- Early warning register template
- Running an early warning meeting
- NEC letter templates
- What is an early warning?
This guide is general information, not legal advice. Check it against your contract.