JCT words and their closest NEC equivalents
A translation guide from familiar JCT terms to NEC4 ECC terms, with the differences that catch out contractors moving across.
On this page
Moving from JCT to NEC means relearning the vocabulary. Many ideas carry across, but the matching NEC term often behaves differently, and that is where mistakes creep in. Read this as a doorway into the NEC4 Engineering and Construction Contract (ECC), not a dictionary. JCT wording varies between forms and editions, and NEC3 names are given where they differ.
Money and change
Start here, because this is where habits clash most.
- Variation becomes a change to the Scope, one of the compensation events (60.1(1)). It is priced from Defined Cost plus Fee by default, not from your contract rates.
- Loss and expense is folded into the same compensation event, so time and money are settled together.
- Interim valuation and certificate becomes an assessment (50.1) followed by a payment certificate (51.1), based on the Price for Work Done to Date.
- Final account becomes the final assessment (53), a feature that arrived with NEC4.
- Pay Less Notice has a counterpart under Option Y(UK)2. Both come from the Construction Act.
- Fluctuations map to Option X1, which is index-based.
- Retention is Option X16, present only if the Client selected it.
- Provisional sums and dayworks have no direct match. They are dealt with through the Scope, later events, or Defined Cost as defined in the Schedule of Cost Components.
Time
- Date for Completion is the Completion Date. It shifts mainly through implemented compensation events or agreed acceleration.
- Practical Completion is Completion, which NEC ties to what the Scope requires. Do not carry JCT custom across.
- Master programme is the Accepted Programme. It must hold far more detail and it is the baseline for judging delay.
- Relevant Event and extension of time become a compensation event that moves the Completion Date. The effect is measured on planned Completion, so it may not equal the days lost on one activity (63.5).
- Sectional Completion is Option X5, and liquidated damages are delay damages under Option X7. Neither exists unless selected.
- Partial possession resembles take over (35), and early take over may be a compensation event (60.1(15)).
Quality, security and disputes
- Rectification Period splits in two: the defects date, when the search for Defects ends, and the defect correction period, which limits how long each fix may take (44.2).
- Certificate of Making Good is the Defects Certificate, which can record Defects still outstanding.
- Performance bond is Option X13. Parent company guarantee is Option X4, and NEC4 refers to the ultimate holding company.
- Contractor's Designed Portion has no separate label. The Scope says what you design, and X15 deals with liability.
- Adjudication, arbitration or litigation sits under the dispute Options: W2 where the Construction Act applies, W1 where it does not. The final tribunal is named in the Contract Data.
- Determination becomes termination (clauses 90 to 93), with a table linking reasons, procedures and payments.
People and documents
- Employer is now the Client (still Employer in NEC3).
- Architect, Contract Administrator or Employer's Agent becomes the Project Manager, who acts for the Client rather than as an independent certifier.
- Clerk of Works is nearest to the Supervisor, who has defined contractual powers over tests and Defects.
- Contract Particulars become the Contract Data, in two parts.
- Specification, drawings and Employer's Requirements all sit in the Scope (the Works Information in NEC3).
- Contract Bills exist only as the Bill of Quantities under Options B and D. Options A and C use an Activity Schedule.
- Contract Sum becomes the total of the Prices, whose meaning depends on the main Option.
Four words that catch JCT people out
- Accept. Acceptance of a programme or design leaves your responsibility intact, and the Project Manager may refuse only for the reasons the contract permits.
- Others. A defined term for people outside the contract.
- Defect. Judged against the Scope and the law, not a general sense of poor work.
- Notify. Many communications must be separate notifications. A line in the minutes may not be enough, so read clause 13 early.
Related guides
- NEC or JCT: how the two contracts differ
- NEC communications under clause 13
- Contract Data explained
- Compensation events in plain English
This guide is general information, not legal advice. Check it against your contract.