NEC Option E: cost reimbursable contracts from the contractor's side

How NEC Option E pays Defined Cost plus Fee with no target, what controls the Client uses, and what you must still do on records and compensation events.

NEC Options and contract types3 min read

On this page
  1. What the arrangement looks like
  2. How the Client keeps control
  3. Compensation events still matter
  4. When it is used
  5. Example: emergency culvert repair
  6. What goes wrong
  7. Related guides

Option E pays you what the work costs, as defined by the contract, plus a Fee. There is no target and no pain or gain share. The Client carries almost all the cost risk and in return gets flexibility and a clear view of what the work costs. That is why it is chosen for work that cannot be pinned down before it starts. This guide follows NEC4 ECC and flags NEC3 differences.

What the arrangement looks like

  • Nothing to price line by line. You do not build an Activity Schedule or Bill. Your tender gives a fee percentage plus the inputs the Schedule of Cost Components needs.
  • Payment follows forecast cost. The Project Manager is the person the Client appoints to run the contract day to day. Each assessment, they estimate your Defined Cost up to the following assessment and add your Fee.
  • The Prices are a forecast. NEC4 treats them as the predicted total Defined Cost of the whole works with the Fee added. NEC3 (E11.2(32)) defines them as Defined Cost plus the Fee, with no forecast element.
  • You forecast too. Contract Data sets how often, and each forecast explains what changed.
  • Your books are open. Clause 52.2 sets the records you must keep, and under 52.3 the Project Manager may examine them during working hours.

How the Client keeps control

With no target to hold you, the Client relies on four things, and you should expect them.

  1. Disallowed Cost. In NEC4 ECC this is 11.2(26) for Options C to E. It removes cost your accounts cannot support, subcontract payments made in error, waste, idle resources, and the cost of fixing defects after Completion.
  2. Procurement control. You send subcontract pricing information to the Project Manager (26.4), and cost caused by ignoring a stated procurement procedure is disallowed.
  3. Forecasts that are read. They warn early that cost is moving, but only if someone challenges them.
  4. Finalising cost as you go. In NEC4, clause 50.9 allows sections of Defined Cost to be settled while the job runs. Review periods apply, and a late decision carries a consequence, so read yours.

You may use retention (Option X16) with Option E. Inflation (X1) and multiple currencies (X3) are not available, since actual cost already captures both.

Compensation events still matter

Do not assume they are irrelevant just because you are reimbursed.

  • They can move the Completion Date and Key Dates, which can affect delay damages if Option X7 applies.
  • They feed the forecast of the Prices that the Client reports against its budget.
  • Missing an early warning can still affect what is assessed and what is allowable.

Run the process, but keep it proportionate.

When it is used

  • Emergency work where you must start before the work can be described.
  • Early investigation where the Scope develops as you learn.
  • Specialist or highly uncertain work where a fixed price would carry a large risk premium.
  • Early contractor involvement, since Option X22 works only with Options C and E.

Example: emergency culvert repair

A culvert collapses under a lane and you are asked to start tomorrow. Nobody can price it. Under Option E you start, record Defined Cost daily, send a weekly forecast, and bill monthly. After a fortnight the cause is clear and the Scope firms up. Some clients would now move the remaining work to a target contract.

What goes wrong

  • Treating it as a blank cheque. A Client that does not resource reviews still pays, but disputes pile up later.
  • Leaving the audit until the end. People move on and paperwork vanishes. Agree monthly reviews and use 50.9.
  • Loose Scope discipline. Your obligation to deliver the Scope remains, and any change to it is still a compensation event.
  • Ignoring the incentive. Fee rises with cost, so a sensible Client will watch your spend. Be open about it.

This guide is general information, not legal advice. Check it against your contract.