NEC time limits at a glance: the periods that catch contractors out
A quick-reference set of NEC time limits for notices, quotations, programmes, payment and completion, with the clause for each and the NEC3 differences.
On this page
If you remember four numbers on an NEC4 Engineering and Construction Contract (ECC), make them these: eight weeks for you to notify a compensation event, three weeks to put in your quotation, and two weeks each for the other side to answer a quotation or a programme. Everything below is the standard, unamended form, so treat it as a starting point and replace it with the figures in your own contract.
A compensation event is the contract's name for something that entitles you to more money or time. The Project Manager is the person the Client appoints to run the contract day to day. Contract Data is the section where project-specific figures are entered.
Where each period comes from
Each line reads: NEC4 ECC / NEC3 ECC / NEC4 subcontract (ECS).
Compensation events
- You notify the event (61.3): 8 / 8 / 7 weeks.
- Project Manager answers your notification (61.4): 1 / 1 / 2 weeks.
- If you then tell them they have not answered, they have a further 2 / 2 / 3 weeks before the event is treated as accepted (61.4).
- You send your quotation (62.3): 3 / 3 / 2 weeks.
- They answer the quotation (62.3): 2 / 2 / 4 weeks.
- You send a revised quotation (62.4): 3 / 3 / 2 weeks.
- Silence on a quotation, after you chase (62.6): 2 / 2 / 3 weeks.
- If the Project Manager assesses it themselves, they get the same time you would have had for the quotation (64.3), then a further 2 / 2 / 3 weeks after you chase (64.4).
For a quotation on a proposed instruction, NEC4 lets the Project Manager name the reply date when they ask (65.2). NEC3 simply uses the usual two weeks.

Programme and early warnings
- First programme: the date in Contract Data (Subcontract Data for the ECS), clause 31.1.
- Project Manager answers a programme (31.3): 2 / 2 / 3 weeks. If you chase, NEC4 ECC allows one more week and the ECS two; NEC3 has no such rule.
- Revised programme when instructed: the period for reply. Regular updates: the interval in Contract Data (32.2).
- First early warning register: one week from the starting date. First early warning meeting: two weeks from it (both 15.2, NEC3 has no fixed period).
- Register reissued after each meeting: one week (15.4).
- The early warning itself has no deadline beyond giving it as soon as you are aware, and the contract sets no time for replying to one.
Payment and final account
- Payment certificate after an assessment date (51.1): 1 / 1 / 2 weeks.
- Payment itself (51.2): 3 / 3 / 4 weeks.
- Pay less notice under Option Y(UK)2: seven days before the final date for payment (Y2.3).
- Final assessment after the Defects Certificate (53.1): 4 weeks / none / 4 weeks.
- Final assessment after a termination certificate: 13 weeks / none / 14 weeks.
Completion and defects
- Certifying Completion: a week after it happens (30.2).
- Take-over: at the latest two weeks after Completion, unless the Client opts out (35.1); a part is certified a week after take-over (35.3).
- Putting a Defect right: the defect correction period in Contract Data (44.2, or 43.2 in NEC3).
- Any other reply the contract requires: the period for reply in Contract Data (13.3).
Cautions before you rely on it
- Z clauses, the extra conditions a Client adds, frequently alter these. Read them first.
- Professional service, term service and short contracts have their own data and may differ.
- Dispute and termination periods are left out because they vary by option and edition. See time limits for disputes.
- A period can sometimes be extended, but only by agreement before the reply is due (13.5, 62.5). Your own eight weeks under 61.3 cannot simply be extended by the Project Manager.
Putting it to work
Diary each date from the day the clock starts, not from the day you noticed. See tracking periods for reply and NEC time bars explained for the routine.
Related guides
- NEC time bars explained
- Tracking periods for reply
- The NEC payment timeline
- Period for reply explained
This guide is general information, not legal advice. Check it against your contract.