NEC4 for subcontractors: shorter clocks, and the main contractor in the middle

What a subcontractor on an NEC4 ECS subcontract needs to know: the shorter periods, who instructs you, how you get paid and what to check before signing.

Tendering and starting a contract4 min read

On this page
  1. Check your form first
  2. In plain English
  3. Your periods under the ECS
  4. Living with the main contractor as your "Project Manager"
  5. Getting paid
  6. Before you sign
  7. How subcontractors get caught
  8. Related guides

As a subcontractor on NEC you work to tighter clocks than the main contractor above you, and the main contractor does the jobs that a Project Manager and Supervisor would do on a main contract. Under the NEC4 Engineering and Construction Subcontract (ECS) you get seven weeks, not eight, to notify a compensation event, and two weeks, not three, to quote.

Check your form first

This guide assumes an unamended ECS. The short subcontract has simpler rules of its own, and a bespoke document that only borrows NEC wording could differ a lot, so read that first.

In plain English

Your periods are shorter so the main contractor has time to pass your information up the chain. Meet them whatever is happening above you.

Your periods under the ECS

Keep this list on your desk.

  • Compensation event you think has happened: tell them within 7 weeks of becoming aware (61.3).
  • Quotation: due 2 weeks after you are told to provide it (62.3). A revised quotation has the same 2 weeks (62.4).
  • First programme: whatever the Subcontract Data says (31.1).
  • Early warning: straight away once you know (15.1).
  • Payment application: in before each assessment date (50.2).

The main contractor gets longer for its own replies: two weeks on a notified event, four on a quotation and three on a programme. That gap is intended, so it can go to the Client's Project Manager and come back. The full list is in NEC time periods.

Living with the main contractor as your "Project Manager"

  • Know who is speaking. A site agent's comment is not an instruction unless the person has authority. Ask who is acting and under which clause.
  • Remember they are on a clock too. They need your quotation to build theirs, so being early usually earns a better conversation.
  • Cause matters. The 60.1 list is similar, but an event the main contractor causes is yours even if it is nobody's event further up. Do not drop a claim because the main contract would not cover it.

Getting paid

  1. Apply every time, before the assessment date, and show your workings (50.2). Skip it and the sum due is calculated on a less favourable footing (50.4).
  2. Get a programme in. Where the Subcontract Data names none, a quarter (25%) of the Price for Work Done to Date is held back until you submit one (50.5).
  3. Know the payment dates. Unless the Subcontract Data changes them, the certificate comes within two weeks of assessment and the money within four (51.1, 51.2).
  4. Check Option Y(UK)2 if the UK Construction Act applies. A paying party that intends to pay less than the notified sum must give notice at least seven days before the final date for payment (Y2.3). If you lawfully suspend work under the Act, that is a compensation event. In the ECS it carries the number Y2.4, which is also used for another clause; in the ECC and PSS it is Y2.5.
  5. Beware pay-when-paid wording in a bespoke form: payment for subcontractors.

Before you sign

Ask these questions of the paperwork:

  1. Which form and edition is this, and has anyone changed the periods?
  2. Does the subcontract programme match the Accepted Programme above you? Request the part that concerns you.
  3. When do you get each access date, and what does each depend on?
  4. Can you see the main contract terms that are meant to apply to you, Z clauses included?
  5. Does the X7 delay damages figure bear any relation to the size of your package?
  6. Have you been given the Site Information for your area?
  7. Does the Fee cover your real overheads, and does anything make a notice harder to give?

How subcontractors get caught

  • Acting on a site agent's say-so. The instruction never comes. Request it, and confirm the conversation by email that day.
  • Holding off until the main contract is resolved. Your seven weeks run regardless of what the Project Manager has told the party above you.
  • Phoning a warning in. Put it in writing or it may not count when it matters. See early warnings for subcontractors.
  • Relying on the main team's records. Keep your own diary, labour allocation and photographs.

NEC3's subcontract is similar in shape, but check its own periods.

This guide is general information, not legal advice. Check it against your contract.