NEC mutual trust and co-operation: what the clause really requires
What the NEC trust and co-operation clause means in daily practice for contractors and subcontractors, and what it cannot do for you.
On this page
The opening duty in an NEC contract asks everyone to do what their role says and to deal with each other openly. People quote it often and usually stretch it too far. It sets expectations for behaviour, but the specific clauses still decide most outcomes.
Two ideas, not one
In NEC3, clause 10.1 combines both duties: the Employer, the Contractor, the Project Manager and the Supervisor must act as stated in the contract and in a spirit of mutual trust and co-operation. NEC4 splits them. Clause 10.1 covers acting as the contract states, and 10.2 covers the spirit of trust and co-operation.
Some templates quote 10.1 for the trust wording, which is right only for NEC3. In NEC4, cite 10.2.
| Half | Plain meaning | Practical effect |
|---|---|---|
| Act as stated | Do what the contract says your role does | NEC describes duties in the present tense ("the Contractor submits"); this turns the description into an obligation |
| Trust and co-operation | Be open and help the other side do its job | Colours how you handle anything the contract leaves to judgement |
The first half applies to the Project Manager and Supervisor as well. A Project Manager who ignores your submission or decides without following the process falls short of the clause, on top of any specific remedy you have.
What good and poor behaviour look like
| Situation | Fits the clause | Does not fit |
|---|---|---|
| You find a mistake in the Client's drawings | Raise it at once | Price around it and spring a claim later |
| A quotation looks incomplete to the Project Manager | Say what is missing and why | Reject it with a one-line reply |
| You know about a compensation event | Notify promptly | Sit on it until the last possible day |
| The Project Manager knows Client supplies will be late | Give an early warning | Stay quiet and hope you run late too |
What it cannot do
- Rescue a missed deadline. If you miss the notification period in clause 61.3, appealing to trust is a weak answer because the specific clause already says what follows.
- Rewrite the deal. It does not make the Client pay more because the job went badly for you. Changes to the contract itself still need clause 12.3.
- Force agreement. You can act in good faith and still disagree firmly. Rejecting a quotation for a sound reason is not a breach.
- Stop either side enforcing the contract. Applying a term, even an unwelcome one, is acting as stated.
Example: the missing survey
Suppose a culvert replacement. Your quotation is due, but you need a survey held by the Client's utility consultant. You ask twice and get nothing. Rather than guess, you write to the Project Manager explaining the gap, and before the deadline you both agree a longer quotation period under clause 62.5.
Both sides behaved well, but notice that the extension came from clause 62.5. The spirit explains why they agreed; a specific clause supplied the mechanism.
Using it well
- Reach for the specific clause first.
- Use kick-off to agree what the spirit means locally: reply standards, how problems get raised, who talks to whom.
- Quote it sparingly. A letter that cites it every time soon sounds empty.
Related guides
- Collaboration under NEC
- The core clauses
- Running an early warning meeting
- Time bars for subcontractors