The nine sections of NEC core clauses and where to look for what

A map of the NEC4 ECC core clauses, section by section, plus the NEC3 differences that catch out people using old templates.

NEC basics for newcomers3 min read

On this page
  1. Start from your question
  2. What matters most in each
  3. Old numbers, new numbers
  4. A habit that saves embarrassment
  5. In plain English
  6. Related guides

Every Engineering and Construction Contract (ECC) carries the same core clauses, whichever main Option sits on top. They run in nine sections, and knowing what each is for tells you where to turn when something happens on site. This guide follows NEC4. It describes what the clauses are about rather than quoting them, so read your own copy, amendments included. The subcontract keeps the numbering but changes the parties.

Start from your question

If you are asking... Go to section
How do we talk to each other, and who can instruct? 1 (clauses 10 to 19)
What must we build, design and manage? 2 (20 to 29)
When do we start, finish and show the programme? 3 (30 to 36)
Who tests, and what happens to Defects? 4 (40 to 46)
How much is due and when? 5 (50 to 53)
What changes the price and the dates? 6 (60 to 66)
Who owns the Plant and Materials? 7 (70 to 73)
Who carries which risk, and what is insured? 8 (80 to 86)
How does it end, and what is paid? 9 (90 to 93)

What matters most in each

1, General. Clause 10 asks everyone to act as the contract says and with mutual trust and co-operation. Clause 13 controls how communications work, 15 deals with early warnings and 17 with unclear documents. Clause 16 lets you suggest a Scope change that would lower the Client's cost.

2, Your responsibilities. Clause 20 is the heart: provide the works as the Scope describes. After it come design, key people, working alongside Others and subcontracting.

3, Time. Clause 30 sets Completion and Key Dates. Clause 31 lists what a programme must show and how the Project Manager (the Client's representative running the contract) may respond. Revisions sit in 32, access in 33, stopping work in 34, take over in 35 and acceleration in 36.

4, Quality. NEC4 begins with your quality system and plan. Tests, searches for Defects and their correction follow.

5, Payment. Assessments, certificates, Defined Cost (the contract's definition of what your costs include) and the final assessment at clause 53. The main Option and, in the UK, Option Y(UK)2 add detail.

6, Compensation events. The list is clause 60, notification 61, quotations 62, assessment 63, the Project Manager's own assessment 64, proposed instructions 65 and implementation 66.

7 to 9. Title matters mostly when you want payment for stored items. Section 8 lists each side's liabilities and the Insurance Table. Section 9 pairs reasons for termination with procedures and payments.

Old numbers, new numbers

Subject NEC3 NEC4
Early warnings 16 15
Your savings proposals none 16
Tests and inspections 40 41
Correcting Defects 43 44
Proposed instructions 61.2 65
Implementing a compensation event 65 66
Final assessment none 53
Core compensation events 19 21

A habit that saves embarrassment

A bare number can mean two different things. Clause 65 is proposed instructions in NEC4 and implementation in NEC3. If you reuse an old letter, or move between edition families, check every reference before it goes out, and state the edition in your own notes.

In plain English

Nine sections cover the job from the first conversation to the last payment. Learn the map, then read closely only the section that matches the problem in front of you.

This guide is general information, not legal advice. Check it against your contract.

Was this useful?