Using a non-NEC subcontract under an NEC main contract
Using your own or the subcontractor's terms below an NEC main contract is allowed, but the mismatches become your risk. Here is what to check.
On this page
A subcontractor has handed you its standard terms, or your procurement team wants a house form. The main contract is NEC. Is that a problem?
The short answer
It is allowed, but it carries a cost. The Project Manager (the person who runs the main contract for the Client) has to accept a non-NEC subcontract under clause 26.3, and every gap between its procedures and your main contract becomes your exposure. The size of that exposure depends on two things: whether the terms include mutual trust wording, and how far their notice periods, change rules and payment dates drift from yours. NEC3 ECC uses the same clause 26 numbers as NEC4.
What to do, step by step
- Send the firm's name under 26.2 and the unpriced documents under 26.3, then wait for the answer. The reply period is the one in your Contract Data.
- Look for the statement about mutual trust and co-operation. If it is missing, the Project Manager is entitled to refuse.
- Look for any term that would prevent you delivering the main contract. That is the only other listed ground for refusal.
- Set the two contracts side by side using the table below, and amend the subcontract wherever the gap would hurt.
- If you are using an NEC form with amendments, still check it. The NEC4 submission exemption only covers an NEC form without amendments beyond those allowed.
Where a mismatch costs money
| Topic | Upstream position | What goes wrong if the subcontract differs |
|---|---|---|
| Notice of events | Eight weeks from awareness (61.3) | The subcontractor can still claim after your own right has lapsed |
| Which events count | The list at 60.1 | You owe for something you cannot recover from the Client |
| Quotations | Three weeks | You have no price when your own is due |
| Early warning | A duty at 15.1 | You miss a warning and risk a statement under 61.5 |
| Payment | Certificate, then payment within three weeks of the assessment date | You pay out before cash arrives, or the terms fail under the Construction Act |
| Disputes | Your W Option | Two adjudicators, two answers |
| Termination | Section 9 | You are stuck with a subcontract after the main contract ends (the NEC4 subcontract has reason R23 for this) |
What to record
- The submission, the acceptance and the date.
- A comparison sheet of notice periods across both contracts.
- Any amendments you negotiated and why.
What not to do
- Do not let the subcontractor's longer notice period stand. It leaves you liable after your own claim has expired.
- Do not assume the Project Manager can refuse because the form is not NEC. That is not a stated reason, although the Scope may restrict which forms you use, so read it.
- Do not appoint before acceptance. Appointing for substantial work first is a termination reason, R13.
When to get help
For a large package, have a commercial manager or lawyer compare the terms before signing. If it is already signed you cannot unilaterally rewrite it, but you can ask the subcontractor to flag anything that might turn into a claim, put that on every meeting agenda, and start your own eight-week count the moment you hear of something.
Example
A fictional roofing firm works to its own terms, which allow twelve weeks to claim for a variation. It raises a design clash in week 11. Your site manager spotted that clash in week 2, so your eight weeks are long gone. The roofer is owed under its terms and you cannot recover a penny from the Client. Seven weeks, as in the NEC subcontract, would have closed that gap.
Related guides
- NEC subcontracts explained
- Back-to-back NEC subcontracts
- Do you need acceptance to appoint a subcontractor
- Preparing a subcontract package
This guide is general information, not legal advice. Check it against your contract.
