Back-to-back NEC subcontracts: matching the time periods above and below

Why NEC4 subcontract periods differ from the main contract, a worked timeline for a change, and where back-to-back quietly breaks.

NEC Options and contract types3 min read

On this page
  1. How the periods line up
  2. A change, week by week
  3. Where back-to-back breaks
  4. Early warnings and programmes
  5. For the main contractor
  6. Other subcontract forms
  7. Related guides

If you are a main contractor, your NEC4 subcontracts are not copies of your main contract, and that is deliberate. The subcontract form (ECS) uses the same clause numbers but different periods, so you have room to pass notices up to the Project Manager and replies back down. If you are a subcontractor, this guide shows why your deadlines are tighter than your main contractor's. Either way, the gaps only help if someone actively manages them.

The figures below are the unamended defaults in the NEC4 ECC and ECS. Amendments often change them, so check your own documents.

How the periods line up

Each line shows main contract / subcontract, with the clause in brackets.

  • Notifying an event (61.3): 8 weeks / 7 weeks. The main contractor gets a week to notify the Project Manager.
  • Reply to a notification (61.4): 1 week / 2 weeks, so the main contractor can take the Project Manager's view first.
  • Quotation due (62.3): 3 weeks / 2 weeks, leaving a week to check the subcontract price and include it.
  • Reply to a quotation (62.3): 2 weeks / 4 weeks, so the main contractor answers after the Project Manager has.
  • Revised quotation (62.4): 3 weeks / 2 weeks, another week in hand.
  • Extra wait before a quotation is treated as accepted (62.6): 2 weeks / 3 weeks.
  • Reply to a programme (31.3): 2 weeks / 3 weeks, time to test it against the main programme.
  • Extra wait before a programme is treated as accepted (31.3): 1 week / 2 weeks.
  • Payment after the assessment date (51.2): 3 weeks / 4 weeks, so money arrives before it has to go out.

A change, week by week

Imagine a steelwork package. The Project Manager tells the main contractor to quote for a change, and the main contractor instructs the subcontractor immediately.

  • Week 0: instructions to quote go out at both levels.
  • Week 2: the subcontractor's quotation is due.
  • Week 3: the main contractor's own quotation is due, containing the subcontract price.
  • Week 5: the Project Manager's reply is due.
  • Week 6: the main contractor's reply to the subcontractor is due.

That leaves exactly a week to absorb the subcontract price and a week to send the answer down. Any slip early on uses up the whole cushion.

Where back-to-back breaks

  • Events do not always match. A delay to the subcontractor may be the main contractor's own co-ordination failure, with no route up to the Client.
  • The tests differ. Each contract's weather or ground conditions event depends on its own data. Compare the entries in both.
  • The main Option may differ. A fixed-price package under a target-cost main contract behaves differently at each level: the subcontract quotation is a price below, but feeds a target above.
  • Dates may not align. Leave space between the subcontract completion date and your own Key Dates. A week lost below is not necessarily a week lost above.
  • Amendments undo the margin. A Z clause shortening your main contract period can leave you with less time than the subcontract gives. Whenever you amend one level, look at the other.

Early warnings and programmes

Warnings must be passed on, because a subcontractor's warning does not reach the Project Manager by itself. See early warnings for subcontractors. Check any subcontract programme against the accepted programme before accepting it: accepting one that does not fit hands the subcontractor an argument later.

For the main contractor

  1. Keep one table per subcontract showing both sets of periods.
  2. Link each subcontract event to its main contract event in your register.
  3. Instruct affected subcontractors the same day the Project Manager instructs you.
  4. Hold off accepting a subcontract quotation until the main outcome is known, unless you are prepared to carry the difference.
  5. Write main contract requirements into the Subcontract Scope, not general wording.

Other subcontract forms

The professional service subcontract uses the same notification and quotation periods as the ECS. The short subcontract (ECSS) uses three weeks to notify and one week to quote. For the term subcontract, read your own copy.

This guide is general information, not legal advice. Check it against your contract.