NEC4 is the current edition of the NEC suite of standard contracts, issued in June 2017. It is a family of forms for building and engineering works, professional services, term maintenance and supply, not one document. The one you are most likely to hold is the NEC4 Engineering and Construction Contract (ECC). The Institution of Civil Engineers owns the suite and develops it through NEC.

The essentials

  • Issued: June 2017. The ECC has since been amended in January 2019, October 2020 and January 2023.
  • Predecessor: NEC3, from June 2005, reprinted with amendments in April 2013.
  • Idea behind it: give both sides a set of procedures for managing risk, change and the programme while the job is running.

What its authors were aiming for

The foreword names three aims: better management in practice, support for newer ways of buying work, and use in more sectors and markets. It was pitched as an evolution. If you know NEC3, most of NEC4 will look familiar.

The additions are mostly around the edges. There is a design, build and operate form, a multi-party alliance form and more subcontract forms. Inside the ECC, some cost items can be agreed and closed off while work continues, and the dispute process now includes a step where senior people from each party meet first. The forms were also lined up more closely with one another.

The four habits you will use every week

  1. Early warning. When you spot something that might raise cost, delay the work or reduce performance, you tell the other side (15.1).
  2. A live programme. You revise it and submit it for acceptance (32.2). Delay is later judged against the Accepted Programme (63.5).
  3. Change as it happens. Compensation events, listed at 60.1(1) to 60.1(21), are notified, quoted for and put into the contract during the job.
  4. Replies on time. Most replies carry a time limit, and a late one can sometimes be treated as acceptance.

Who ends up on it

Clients, consultants, contractors, subcontractors and suppliers across infrastructure, utilities, transport and buildings. In the UK, the Government Construction Board endorses the NEC4 documents for suitable public sector projects. If you are a subcontractor, you probably did not pick NEC4: the party above you did. Your form may be the Engineering and Construction Subcontract or a professional services contract, with its own numbers and periods.

Misreadings to avoid

  • "We're on NEC4" is incomplete. Ask which form and which main Option.
  • The job may not use NEC4 at all. A contract keeps whichever edition it names, and NEC3 is still live on existing contracts and frameworks.
  • The book is not the contract. Your Contract Data (the section where your project's dates, periods and rates are filled in), the Scope and any Z clauses make your agreement unique.
  • It is a refinement, not a replacement. Numbers shifted and names changed, but the method is the same.

Which edition have you got?

  1. Open Contract Data part one. The opening line names the conditions and edition.
  2. Check the date: NEC4 starts at June 2017, NEC3 ECC is dated 2005 or 2013.
  3. Listen to the vocabulary. Client and Scope suggest NEC4; Employer and Works Information suggest NEC3. One catch: the NEC3 professional services contract already used the word Scope.
  4. Find the early warning clause. NEC4 puts it at 15, NEC3 at 16.

This guide is general information, not legal advice. Check it against your contract.