NEC4 compensation events listed one by one in plain English

All 21 core NEC4 compensation events in clause 60.1, plus the Option events, with who normally notifies each and how to read the list.

Compensation events and change4 min read

On this page
  1. Who gives the notice
  2. The 21 core events
  3. Extra events that depend on Options
  4. Using the list sensibly
  5. Related guides

If you are on an NEC4 Engineering and Construction Contract, clause 60.1 holds 21 core compensation events. A compensation event is something the Client carries the risk for, so it triggers a reassessment of your Prices and dates. The summary below uses short paraphrases. Many entries carry exceptions, so always check the exact test in your own contract before relying on one.

Who gives the notice

The rule follows the cause. If the event comes out of an instruction, certificate, notification or reversed decision, clause 61.1 makes the Project Manager (the person the Client appoints to run the contract day to day) responsible for notifying it. Anything else, you notify yourself under 61.3. The "usual" column below is a guide, not a rule.

The 21 core events

No. Short description Usual notifier
1 Instruction that changes the Scope (the description of what you must deliver). Excluded: accepting a Defect, or altering your design for your own reasons PM
2 You get a part of the Site later than both its contractual access date and the programme date You
3 Client-provided items turn up after the date the Accepted Programme assumes You
4 Instruction to halt work, hold it back, or move a Key Date PM
5 The Client or Others (third parties) work at times, or on terms, the Accepted Programme and Scope did not anticipate, or do unmentioned work on Site You
6 A reply to your communication from the PM or Supervisor comes too late You
7 PM directs how to handle an object of value or historic interest PM
8 PM or Supervisor changes a decision already given PM
9 An acceptance is held back for a reason outside those the contract allows You
10 A Defect search finds nothing, apart from the case where your own short notice of blocking work caused the search Either
11 Supervisor testing or inspection causes needless hold-up You
12 Ground or other physical conditions (not weather) that an experienced contractor could not sensibly have allowed for. Only the excess counts You
13 A month of weather rarer than a one-in-ten-year event in the weather data. Only the excess counts You
14 A risk the contract states as the Client's occurs You
15 Part is taken over and certified before Completion PM
16 Materials, facilities or samples the Scope promised for testing are not provided You
17 PM corrects an earlier stated assumption PM
18 Client breaches the contract and nothing else on the list fits You
19 A freak occurrence neither side could prevent halts completion, and no other entry covers it You
20 PM rejects a quotation for a proposed instruction PM
21 An extra event written into Contract Data Varies

Extra events that depend on Options

  • Options B and D: a quantity differing from the Bill of Quantities (60.4), a quantity change that delays Completion or a Key Date (60.5), and a corrected Bill mistake (60.6).
  • X2: a change in law after the Contract Date (X2.1).
  • X12: the Core Group altering the Partnering Information, or you reprogramming to a new timetable (X12.3).
  • X14: a late advanced payment (X14.2).
  • X15: you fixing a Defect you are not liable for (X15.2).
  • Y(UK)2: you suspending work as the Construction Act permits (Y2.5).

Z clauses often rewrite the list, and 60.1(21) exists precisely so extra events can be named in Contract Data.

Using the list sensibly

  1. Check dates in the Accepted Programme. Events 2, 3 and 5 depend on them. If your programme omits them, the event is harder to prove.
  2. Try specific events before number 18. The breach entry only fills gaps.
  3. Read "only the excess" carefully. For 12 and 13, you recover what goes beyond a reasonable allowance, not the whole cost of poor ground or bad weather.
  4. Do not treat NEC3 as identical. Numbering to 19 mostly matches, but defined terms differ.

This guide is general information, not legal advice. Check it against your contract.