NEC4 compensation events listed one by one in plain English
All 21 core NEC4 compensation events in clause 60.1, plus the Option events, with who normally notifies each and how to read the list.
On this page
If you are on an NEC4 Engineering and Construction Contract, clause 60.1 holds 21 core compensation events. A compensation event is something the Client carries the risk for, so it triggers a reassessment of your Prices and dates. The summary below uses short paraphrases. Many entries carry exceptions, so always check the exact test in your own contract before relying on one.
Who gives the notice
The rule follows the cause. If the event comes out of an instruction, certificate, notification or reversed decision, clause 61.1 makes the Project Manager (the person the Client appoints to run the contract day to day) responsible for notifying it. Anything else, you notify yourself under 61.3. The "usual" column below is a guide, not a rule.
The 21 core events
| No. | Short description | Usual notifier |
|---|---|---|
| 1 | Instruction that changes the Scope (the description of what you must deliver). Excluded: accepting a Defect, or altering your design for your own reasons | PM |
| 2 | You get a part of the Site later than both its contractual access date and the programme date | You |
| 3 | Client-provided items turn up after the date the Accepted Programme assumes | You |
| 4 | Instruction to halt work, hold it back, or move a Key Date | PM |
| 5 | The Client or Others (third parties) work at times, or on terms, the Accepted Programme and Scope did not anticipate, or do unmentioned work on Site | You |
| 6 | A reply to your communication from the PM or Supervisor comes too late | You |
| 7 | PM directs how to handle an object of value or historic interest | PM |
| 8 | PM or Supervisor changes a decision already given | PM |
| 9 | An acceptance is held back for a reason outside those the contract allows | You |
| 10 | A Defect search finds nothing, apart from the case where your own short notice of blocking work caused the search | Either |
| 11 | Supervisor testing or inspection causes needless hold-up | You |
| 12 | Ground or other physical conditions (not weather) that an experienced contractor could not sensibly have allowed for. Only the excess counts | You |
| 13 | A month of weather rarer than a one-in-ten-year event in the weather data. Only the excess counts | You |
| 14 | A risk the contract states as the Client's occurs | You |
| 15 | Part is taken over and certified before Completion | PM |
| 16 | Materials, facilities or samples the Scope promised for testing are not provided | You |
| 17 | PM corrects an earlier stated assumption | PM |
| 18 | Client breaches the contract and nothing else on the list fits | You |
| 19 | A freak occurrence neither side could prevent halts completion, and no other entry covers it | You |
| 20 | PM rejects a quotation for a proposed instruction | PM |
| 21 | An extra event written into Contract Data | Varies |
Extra events that depend on Options
- Options B and D: a quantity differing from the Bill of Quantities (60.4), a quantity change that delays Completion or a Key Date (60.5), and a corrected Bill mistake (60.6).
- X2: a change in law after the Contract Date (X2.1).
- X12: the Core Group altering the Partnering Information, or you reprogramming to a new timetable (X12.3).
- X14: a late advanced payment (X14.2).
- X15: you fixing a Defect you are not liable for (X15.2).
- Y(UK)2: you suspending work as the Construction Act permits (Y2.5).
Z clauses often rewrite the list, and 60.1(21) exists precisely so extra events can be named in Contract Data.
Using the list sensibly
- Check dates in the Accepted Programme. Events 2, 3 and 5 depend on them. If your programme omits them, the event is harder to prove.
- Try specific events before number 18. The breach entry only fills gaps.
- Read "only the excess" carefully. For 12 and 13, you recover what goes beyond a reasonable allowance, not the whole cost of poor ground or bad weather.
- Do not treat NEC3 as identical. Numbering to 19 mostly matches, but defined terms differ.
Related guides
- What is a compensation event
- Compensation event examples
- Weather as a compensation event
- Physical conditions explained
This guide is general information, not legal advice. Check it against your contract.