NEC4 Term Service Contract (TSC): working on call-off maintenance
How the NEC4 Term Service Contract differs from the construction contract: Service Manager, Task Orders, the plan and the compensation events.
On this page
A Client who wants a service delivered across a set term, such as keeping a road network, a building stock or plant maintained, will usually use the NEC4 Term Service Contract (TSC). There is no single finish date. The Client's Service Manager calls off pieces of work as Task Orders, and time is managed task by task. If you are used to the construction contract, expect different names and a different rhythm.
Words you will meet
| Term | What it means for you |
|---|---|
| Service Manager | Does the jobs the Project Manager and Supervisor do on a construction contract |
| Affected Property | The thing you carry out the service on |
| Service Areas | Where you work |
| Service Period | The term of the whole contract |
| Task | One defined piece of work within the service |
| Task Completion Date | The date for a single Task, set in its Task Order |
| The plan | Your programme covering the whole service |
| Price for Service Provided to Date | What you have earned so far, in term contract language |
Task Orders are the engine
The key mechanism sits in clause 19. Each order tells you which Task to do, between which dates, with any delay damages attached, and the Service Manager can request a quotation beforehand (19.1). An order arriving is not a compensation event; an instruction altering a Task is (60.1(1)). See task orders explained.
The plan
Unless a plan is already identified, you send a first plan for acceptance inside the period stated in the Contract Data (31.1). What it must show is listed in 31.2, and that includes every Task and its dates. The Service Manager's answer, and what silence means, are in 31.3, while later revisions follow 32.1 and 32.2. Single Tasks can need a programme of their own (33 and 34).
Watch out: if no plan is identified, a quarter of the running total is withheld at each assessment until you submit a first plan (50.5).
Main Options
There are three: Option A (priced, with a Price List), Option C (target, with a Price List) and Option E (cost reimbursable). On A and C there are stated cases where a final quantity different from the Price List counts as a compensation event (60.2).
Secondary Options are different too: X19 allows termination by either side, X23 extends the Service Period and X24 deals with accounting periods. X5, X6, X7, X9, X14, X15, X16 and X22 are not available. In NEC3, X19 meant Task Orders. In NEC4 Task Orders are core, so do not mix the two up.
Compensation events: 18, in their own order
Several are particular to this form:
- You are refused access to the Affected Property: 60.1(2).
- An order lands after the start date written in it: 60.1(4).
- The Affected Property itself is altered: 60.1(11).
- A mistake in the Price List is put right: 60.1(16).
- The Service Manager rejects your quotation for a proposed instruction, or declines to instruct a Task: 60.1(17).
Missing altogether are events for physical conditions, weather, objects of interest, take over, searches and prevention. If you come from construction work, price those risks with that in mind.
Other differences
- Tests are handled by the Service Manager.
- Defects have no defects date or Defects Certificate. They are notified under 43.1 and corrected quickly enough to limit harm (43.3).
- Payment uses the ECC's numbering, with the final assessment (53.1) falling after the Service Period ends.
- Early warning is triggered by a rise in the total of the Prices, disruption to when the service happens, the service working less well, or higher cost to you.
Traps
- Treating a Task Order as a variation. It is the normal way work is ordered.
- Accepting backdated orders. Work started on a phone call can create a 60.1(4) argument, so record when the order reached you.
- A weak Price List. If it does not match how work is really ordered, nearly every Task needs a quotation.
- Facilities services may fit the separate Facilities Management Contract better.
Related guides
- Task orders explained
- How to choose the right NEC contract
- Time bars explained
- Early warnings for subcontractors
This guide is general information, not legal advice. Check it against your contract.