NEC4 Short Contract (ECSC): when it fits and what it leaves out
What the NEC4 short form for works contains, what it drops compared with the full contract, and the traps for contractors working under it.
On this page
The NEC4 Engineering and Construction Short Contract (ECSC) is the lighter form for simple works. It runs directly between the Client and you, with no Project Manager and no Supervisor: the Client does those jobs itself. It keeps the NEC style and a similar clause pattern but removes most of the administration. That is good news if the job really is simple, and a problem if it is not.
Does the job suit it?
It tends to fit when all of these are true:
- the work can be fully described before you start,
- ground, access and interface risks are low,
- there is little phasing, no need for Key Dates (fixed milestone dates) and no sectional handover,
- a simple Price List (a list of rates) suits the payment,
- the Client is content to give its own instructions and assessments, and
- no bonds or secondary Options are needed. Retention can still apply, because the form has its own rule at 50.7.
Think resurfacing, minor refurbishment, fencing or simple drainage. No clause sets a value limit, so price is only a rough guide.
What you lose compared with the full ECC
| In the full contract | In the short form |
|---|---|
| Project Manager and Supervisor | None; the Client acts |
| Main Options A to F | None; a Price List only |
| Secondary Options | None; Construction Act terms are written into the conditions |
| Early warning register and meetings | None; either side raises a warning (15.1) and both then agree a response together (15.2) |
| Accepted Programme | None; programmes are sent as the Scope asks (31.1) and nobody accepts them |
| 21 compensation events | 12, numbered differently |
| Revised quotations | Simpler: the Client accepts or makes its own assessment |
| Formal final assessment | None; the last assessment stands as final |
Compensation events in the short form
The list at 60.1 is much shorter. Broadly it gives you a route for: an instructed change to the Scope (but not one made to accept a defect); the Client late with site access or with something it must supply; being told to stop or hold off; the Client acting against the working conditions in the Scope; a communication left unanswered for too long; the Client reversing a decision it gave; ground or other physical conditions beyond what a competent contractor would allow for (you get only the excess); weather that halts all work beyond the allowance in the contract; fixing a wrong assumption about an earlier event; an unforeseeable event outside both parties' control; and an instruction that corrects a mistake in the Price List. The numbering is different, so ECC clause references do not carry over.
The procedure
Either party may raise a suspected event (61.1). When you raise one, your quotation travels with the notice. When the Client raises one, you have a set time to quote (61.2). The Client then says yes, or says no and substitutes its own figure (62.2). Silence from the Client can leave your quotation treated as accepted (62.3). Fail to quote and the Client prices it itself (62.4). Notify too late and the Prices and Completion Date stay as they were (61.3).
The unamended periods are shorter than in the full contract: four weeks for you to notify, a single week to quote after the Client's notice, two weeks for the Client's answer, and one week for its own assessment where you have not quoted.
On payment, you send your application ahead of each assessment date, and the Client then works out what is due (50.1). Late or corrected payments carry interest (51.2).
What goes wrong
- Thinking short means soft. It is a full contract, and the time limits bite just as hard.
- No accepted programme. If the Scope is silent on programmes, you have nothing to measure delay against. Ask for a programme requirement before signing.
- Bolting on extras by Z clause. If the job needs a Project Manager, Key Dates and delay damages, use the full form.
- A silent Client. Without a Project Manager, one overloaded Client employee can stall everything. A missed reply can itself be a compensation event under 60.1(6).
- The wrong subcontract. If you sublet, use the matching short subcontract and check its periods rather than assuming they match.
Related guides
- How to choose the right NEC contract
- Time bars explained
- What is a compensation event?
- Choosing secondary options
This guide is general information, not legal advice. Check it against your contract.