What an NEC contract is and what it expects from you on site
A newcomer's definition of an NEC contract, the four habits it demands, and how to work out which version you have been handed.
On this page
If you have been put on a job and told "it's NEC", you have been handed a published set of contract conditions from the NEC family, which belongs to the Institution of Civil Engineers. Most often it is the Engineering and Construction Contract (ECC). It does more than record who owes what: it builds a working routine into the agreement, and the people on site are expected to follow it.
The four habits it expects
Clause numbers below are from the NEC4 ECC.
- Say so early. As soon as you know of something that could push up cost, delay the job or hurt quality, you tell the other side. That is an early warning (15.1; it is 16.1 in NEC3).
- Keep the programme alive. You submit a detailed programme, then keep revising it (clauses 31 and 32). It is later used to measure delay.
- Deal with change as it happens. Events that are not your risk are called compensation events. They are priced and settled during the job, not saved for the end.
- Watch the clock. Both you and the Project Manager (the person the Client appoints to run the contract day to day) have set periods to act in. Being late has consequences, and a contractor who waits more than eight weeks to notify a compensation event can lose it (61.3, with limited exceptions).
Quick facts
| Question | Answer |
|---|---|
| Who publishes it? | NEC, part of the Institution of Civil Engineers |
| First appeared | 1993, after a consultation edition in 1991 |
| Editions you will meet | NEC4 (June 2017) and NEC3 (2005), which is still on many live contracts |
| What it covers | Works, professional services, term services, supply and the matching subcontracts |
| Where it is common | UK infrastructure and public sector work, plus other sectors and countries |
What it is not
- Not one pricing method. Under Option A you price activities. Under Option E you are paid your cost plus a Fee. "NEC" alone tells you nothing about whether the price is fixed, so always ask which main Option applies.
- Not one document. It is the standard clauses plus the choices and project details added for your job. The contract structure guide shows how the pieces fit.
- Not only for civil engineering. It started there but is also used for buildings, maintenance and services.
- Not automatically friendly. It requires mutual trust and co-operation (10.2), but that only happens if the people involved make it happen.
- Not required by law. A client policy or framework might insist on it, but no statute does.
Which NEC contract have you got?
Find the front page of the Contract Data (the part of the contract where project-specific dates, periods and figures are filled in) or the agreement, and look for four things.
- Edition and date. NEC3 documents talk about an Employer, NEC4 about a Client.
- Form. ECC, the subcontract (ECS), a professional services contract, a term service contract or a short contract.
- Main Option. For the ECC, a letter from A to F.
- Other Options. The dispute Option, any X or Y secondary Options, and any Z clauses, which are extra conditions that change the standard terms.
Write those four answers on the inside of your file. Almost every later question depends on them.
In plain English
An NEC contract is a standard rulebook that expects you to warn early, keep the programme current, settle change quickly and reply on time. Your own copy, with its Options and Z clauses, is the version that counts.
Related guides
- NEC contracts explained step by step
- How an NEC contract is structured
- An NEC guide for contractors
- What is NEC4?
This guide is general information, not legal advice. Check it against your contract.