What the Client carries under NEC: the clause 80.1 list
The risks NEC puts on the Client, how taking over changes them, and how a Client liability becomes a compensation event for the contractor.
On this page
NEC4 clause 80.1 is the Client's side of the risk ledger. When something on that list happens, the Client carries the consequences and you, as Contractor, can claim time and money. In NEC3 the same idea appears as the Employer's risks, also at 80.1.
In plain English
The Client carries what it or its people did wrong, what it designed or supplied until you accept it, the unavoidable side effects of the building itself, and a few catastrophic events nobody controls. Whatever is left tends to land on you.
The list, grouped by cause
Things the Client side did
- A fault by the Client or its people, such as a separate Client contractor flooding your excavation.
- Negligence or breach of duty by the Client's people causing a third-party claim, such as the Client's security firm reversing into a neighbour's gate. You are expressly not one of the Client's people.
- A design fault in the Scope the Client provided, or in an instruction changing it: a Client-designed beam turns out undersized.
Things nobody could avoid
- Third-party claims caused by the unavoidable effect of the works or of using the Site, for example a neighbour's loss of light from a building built exactly to design.
- War and similar events, strikes and riots that go beyond your own workforce, and radioactive contamination.
Things about property and handover
- Client-supplied Plant and Materials until you receive and accept them.
- Parts already taken over (subject to the exceptions below).
- Works and items the Client keeps on Site after a termination.
- The Client's other property, unless the damage is connected with Providing the Works. A storm hitting an existing building you are not touching is the Client's.
Anything added in the Contract Data (the part of the contract where project-specific figures and extra terms are filled in).
Taking over does not move everything
Until the Defects Certificate, damage still falls to you if it was caused by a Defect that already existed at take over, by an earlier event that was not the Client's liability, or by your own activities on the Site afterwards. A floor that cracks from a pre-existing Defect stays with you even though the Client has moved in.
Why it matters to you
An event on the list is a compensation event under 60.1(14), so you can recover time and money for its effect on the works. You can also recover from the Client sums you paid to third parties. The event must still be notified within the period in clause 61.3.
What changed from NEC3
| Point | NEC3 | NEC4 |
|---|---|---|
| Heading | Employer's risks | Client's liabilities |
| Fault of the paying party | Folded into the claims item | Listed separately |
| Client's other property | Not listed | Listed, with an exception |
| Your side | Whatever the Employer does not carry | Its own list |
Reading it on a real job
- Start with the Contract Data. Extra liabilities are a common way to move a named risk, such as asbestos in a defined area.
- Check Z clauses (project-specific additions to the standard conditions), since some Clients remove or qualify items.
- Ask whose fault or event it was, and who employed the person responsible. Your subcontractors answer to you.
- Photograph the damage and write an incident note straight away. Cause evidence decides most of these arguments.
Common errors
- Treating "unavoidable" as including careless working. Noise that sensible methods could have cut is not unavoidable.
- Confusing this list with weather or ground conditions, which have their own events at 60.1(13) and 60.1(12).
- Expecting the Client's insurer to pay. The Insurance Table covers your liabilities; the Client must arrange its own cover.
Related guides
- The contractor's liabilities under NEC
- Insurance under NEC
- What is a compensation event?
- Reading Z clauses
This guide is general information, not legal advice. Check it against your contract.