What a compensation event is and why it matters to your price and programme

A plain explanation of NEC compensation events: what they cover, how they replace variations and extensions of time, and a quick test for site events.

Compensation events and change3 min read

On this page
  1. In plain English
  2. What the name hides
  3. Where to find the list
  4. Where your old vocabulary goes
  5. Why it decides the outcome of the job
  6. A five-question test for site events
  7. What a compensation event is not
  8. Related guides

A compensation event is NEC's single route for changing your price and your dates. It is an event, named in the contract, whose risk sits with the Client rather than with you. When one happens and it affects your cost or your completion, the contract reassesses the Prices and the Completion Date so you are not left worse off.

In plain English

Think of it as the contract's built-in change mechanism. Instead of a separate variation, an extension of time and a loss claim, NEC deals with price and time together, event by event, close to when each one happens.

What the name hides

The label suggests a damages claim or a guaranteed payment. It is neither. An event can add money, add time, add both or, in limited cases, reduce the Prices. The result is worked out from the effect on your Defined Cost (the actual cost of the work, as the contract defines it) plus the Fee (your agreed percentage for overheads and profit).

Where to find the list

In the NEC4 Engineering and Construction Contract, the main list is in clause 60.1 and runs to 21 entries. Typical entries include a Project Manager's instruction altering the Scope (the document setting out what you must deliver), ground nobody could sensibly have predicted, very rare weather, and the Client being late against the Accepted Programme (the programme the Project Manager has accepted). Your chosen Options and Contract Data can add more. If an event is on none of those lists, it is not a compensation event, although 60.1(18) mops up a Client breach that nothing else covers. Our list of the NEC4 events goes through each entry.

Where your old vocabulary goes

Familiar from JCT or bespoke forms Where it lives in NEC
Variation or change order 60.1(1), a Project Manager's instruction altering the Scope (called Works Information in NEC3)
Extension of time Part of the same event: the Completion Date moves if planned Completion does
Loss and expense Part of the same event: the knock-on to your Defined Cost
Latent ground claim 60.1(12)
Client breach 60.1(18), only where no specific entry fits

Clause 63.6 confirms that the changes to Prices and dates are your only entitlement for that event, so there is no second claim at the end of the job.

Why it decides the outcome of the job

Most NEC contracts are won or lost commercially on their compensation events, and both sides are on a clock. If you miss the eight weeks in clause 61.3 for notifying an event, you can lose it altogether. If the Project Manager misses a reply, a quotation can be treated as accepted. Neither outcome depends on how strong the underlying event was.

A five-question test for site events

  1. Is the event on the list in your contract, including Options and Contract Data additions?
  2. Has it happened, or is it expected?
  3. Is it free of any fault on your side?
  4. Will it move your cost, your completion or a Key Date?
  5. If you are the one notifying, are you inside the time allowed?

Five yeses means it should go forward to a quotation. Write down the sub-clause in your notice.

What a compensation event is not

  • Not an early warning. A warning raises a risk and never starts this process. Both may be about one problem, yet they are separate notices.
  • Not just extra work. A late drawing or a test that holds you up can qualify without adding any task at all.
  • Not a lump at the end. Each event is settled by itself and normally stays settled.
  • Not a cure-all. Mistakes of your own, and risks the contract leaves with you, remain yours.

This guide is general information, not legal advice. Check it against your contract.