NEC insurance: what the contractor must arrange and prove

A plain guide to the Insurance Table, certificates, joint names, subrogation and excesses under NEC, with a start-of-job checklist.

Early warning and risk3 min read

On this page
  1. In plain English
  2. What the Insurance Table asks for
  3. Your duties, in order
  4. Traps
  5. A short example
  6. Start-of-job checklist
  7. Related guides

Insurance is dealt with in clauses 83 to 86 of the NEC4 Engineering and Construction Contract (84 to 87 in NEC3). You provide the cover in the Insurance Table and prove it with certificates, unless the Contract Data says the Client provides it. If either party fails to insure, the other may arrange it and recharge. Insurance runs alongside the liability rules rather than replacing them: a liability stays where the contract puts it, even if the insurer declines the claim.

In plain English

Buy the cover the Table asks for, show it on time, make sure the insurers cannot turn on the Client, and price the excess, because whatever the insurer will not pay is still yours.

What the Insurance Table asks for

The Contract Data states the amounts. Tender documents often ask for more.

Risk Minimum cover
Works, Plant and Materials Replacement cost, plus the stated amount for items the Client supplies
Equipment Replacement cost
Third-party property damage, and injury or death of anyone who is not your employee, linked to Providing the Works The Contract Data figure per event, with cross liability so each party is covered separately
Your employees The higher of the legal requirement and the Contract Data figure, for any one event

Professional indemnity is absent from the Table. Where design matters it is requested separately, and NEC4 Option X15 covers it.

Your duties, in order

  1. Take out the Table cover plus anything extra in the Contract Data (83 in NEC4, 84.1 in NEC3).
  2. Insure in joint names, with the cover lasting until the Defects Certificate or a termination certificate (83; 84.2).
  3. Send certificates signed by the insurer or broker before the starting date and at every renewal (84.1; 85.1).
  4. Make sure insurers waive subrogation (84; 85.2).
  5. Follow the policy conditions yourself (84; 85.3).
  6. Expect the Client to insure and charge you if no certificate arrives (85; 86.1).

Where the Client insures certain items, you have matching rights (86; 87).

Two edition differences. NEC4 lets the Client refuse certificates on two grounds: the cover does not comply, or the insurer is too weak financially to stand behind it. NEC3 gives non-compliance only. And the NEC4 subcontract text does not require joint names for the fourth item, your own staff, where NEC3 makes no exception.

Traps

Subrogation. An insurer that has paid out may chase whoever caused the loss. A waiver stops it pursuing the protected people, fraud aside. Without it a joint-names policy loses much of its value, so ask the broker to point to the words.

Uninsured amounts. NEC3 says in 85.4 that a sum the insurer does not pay remains with the party at risk. Assume the same principle in NEC4. Excesses and exclusions belong in your price.

Annual policies. They can meet the Table if the terms fit. Check that renewal falls inside the certificate cycle and that your type of work is not excluded. A lapse can let the Client insure and recharge you.

A short example

An Option C highway depot requires £10 million third-party cover per event and £5 million employer's liability. Your annual policy gives the £10 million but carries a £250,000 excess for work beside a live road. A third party claims £180,000. The insurer pays nothing because the claim sits inside the excess, yet the liability is still yours. Then ask whether the cost counts as Defined Cost on Option C, using the Defined Cost guide.

Start-of-job checklist

  • Compare the Table and Contract Data with your real policies.
  • Confirm joint names, cross liability and the waiver.
  • If the job is an existing building, find out who insures it; the Contract Data often alters this.
  • Diarise certificates and every renewal up to the defects date.
  • Tell your insurer promptly about any incident.
  • Pass the requirements to subcontractors.
  • Ask your broker to review the wording. This is not insurance advice.

This guide is general information, not legal advice. Check it against your contract.

Was this useful?