Your own designer is late: who carries the cost?
If a designer you appointed delivers late, the delay is normally yours. Here is what to do now, who pays by main Option, and when a Client cause exists.
On this page
The design consultant you appointed is behind with drawings, and the job is starting to feel it. You are wondering if the Client takes any of the risk.
The short answer
In most cases you carry it. Where the Scope says you design the element, your designer is treated as part of your own side, which means its slippage earns you no event, no added time and no movement in the Prices. Clause 26.1 keeps you responsible for work you subcontract. Still give an early warning now, because the Project Manager may be able to help, and check whether any part of the delay has a Client cause.
What to do, step by step
- Give an early warning. Clause 15.1 reaches any matter that might delay Completion or a Key Date, including problems of your own making. The Project Manager might allow a different order of work or bring forward a Client decision.
- Ask the designer why, in writing. If it blames missing Client information, get the dates.
- Notify any part with a Client cause. The eight weeks in clause 61.3 is already running on that part. Argue it separately from your designer's own slippage.
- Reflect it in your next programme. A revised programme must show how you intend to handle delays. Hiding the problem in the hope of catching up backfires.
- Write to the designer under its appointment. Any recovery comes through the consultant's appointment, not the NEC contract. Check what it says on programme, liability and notice.
Who pays, by main Option
| Option | Extra cost | Delay to Completion |
|---|---|---|
| A and B | Yours; the Prices stay fixed | Yours, with delay damages possible under Option X7 |
| C and D | Reimbursed as Defined Cost if allowed, but the target stays put, so your share absorbs it | Yours |
| E | Reimbursed with Fee if not disallowed | Yours; the Completion Date stays |
Under C, D and E, read the list of Disallowed Cost. Sums you paid the designer beyond what its appointment demanded are a classic trap.
What changes the answer
| Why the designer was late | Likely position |
|---|---|
| Under-resourced or started late | Yours |
| Your team was late with coordination or surveys | Yours |
| Client information arrived after its programme date | 60.1(3) may apply to that slice alone |
| A utility or other third party ran late against programme times | 60.1(5) may apply |
| The Project Manager instructed a change to the Client's own Scope design | 60.1(1) |
| The Project Manager did not answer your design submission in time | 60.1(6) may apply |
| The Project Manager rejected your design on a ground the contract permits | Yours |
What to record
- A dated trail from the designer separating each cause.
- When Client information was due and when it came.
- Your submission dates and the Project Manager's replies.
- Programme revisions showing the critical path.
What not to do
- Do not present your designer's delay as a Client problem. The Project Manager will read the design split in the Scope first.
- Do not notify the whole delay. Claim only the days caused by the Client-side cause.
- Do not leave the delay out of your programme.
- Do not rebuild the cause trail months later. Do it as you go.
When to get help
Involve a commercial manager if a mixed delay needs splitting, and a planner to prove the effect on the critical path. Take legal advice if the designer's contract limits what you can recover.
Example
A fictional Option A pumping station. Your structural designer is three weeks late. Ten days of that trace to survey data the Client issued after its programme date. You notify only those ten days under 60.1(3) and take the rest as your own. Telling the Client early, with a recovery plan, often lets it shift its own tasks. Discovering the slip from a drawing register leaves it no room.
Related guides
- Contractor's design under NEC
- Late drawings: can you claim a compensation event?
- The Scope explained
- What is an early warning?