NEC Working Areas: why where your people sit affects what you recover
What NEC Working Areas are, the two tests they must pass, and how listing the right places in Contract Data protects your cost recovery.
On this page
If you work on a cost-based NEC contract, the question "is that cost inside the Working Areas?" decides what you can charge for. Working Areas are the Site plus any extra places you name in Contract Data, provided they are needed for this job and used for nothing else. They can be wider than the Site. The definition is in clause 11.2 (item 18 in NEC3 ECC), and the matching entry is in part two of Contract Data, the part you complete.
Two tests for every extra place
- Is it needed to provide the works? Convenience is not enough. If you would use the place anyway, it fails.
- Is it used only for this contract? A shared office, with other projects run from it, fails.
In NEC3 the entry reads as the Site plus your list. The NEC4 subcontract definition opens with the Site. The Site is always included.
What turns on it
- People costs. Under the full schedule, a person counts in full if they normally work in the Working Areas, and otherwise in proportion to the time they spend there.
- Equipment costs. These follow the time equipment spends in the Working Areas.
- Design and fabrication. Work done outside is priced under separate sections and rates.
- Ownership. Plant and Materials taken into the Working Areas pass to the Client so far as you own them (70.2).
- Sharing space. You share the Working Areas with Others as the Scope says (25.1).
Example: a highways junction on Option C
Your entry names the Site and a rented project office in the next town. The regional base, forty miles off, houses a commercial manager and a planner.
| Person | Base | Result |
|---|---|---|
| Project engineer | Rented project office | Inside, so recoverable |
| Commercial manager | Regional base, visits one day in five | Only a fifth of the cost |
| Planner | Regional base all week | Not a people cost; the Fee covers them |
Later you want both into a larger office on the job. You propose it, and the Project Manager, who is the person the Client appoints to run the contract, runs the two tests. If that office also supports another project, expect a refusal.
Adding an area later
You propose it and the Project Manager decides (16.3 in NEC4, 15.1 in NEC3). Refusal is allowed only where the place is not necessary or is used for other work. An accepted area does not create a compensation event or entitle you to payment for the space. It only shifts the cost boundary, so agree a start date in the acceptance.
Slips to avoid
- Assuming it equals the Site. A compound beyond the Site can be a Working Area, but getting to it is not the Client's responsibility unless the Scope says so, and late-access events relate to the Site.
- Naming head office. With other work going on, it fails the second test. A dedicated team room might pass if the facts allow.
- Leaving the entry stale after an office move, which an audit will pick up.
- For the Client's side: on cost-based Options, check what each extra area could bring in.
Read this with the Site definition when you settle boundaries.
Related guides
- Contract Data explained
- Defined Cost, Fee and Disallowed Cost
- Schedule of Cost Components
- Access dates and starting work
This guide is general information, not legal advice. Check it against your contract.