What to raise as an NEC early warning: examples and a quick test

Practical examples of matters that need an NEC early warning, a four-question test for borderline cases and what does not need one.

Early warning and risk3 min read

On this page
  1. A four-question test
  2. Examples
  3. Easy to overlook
  4. The optional warning on your own cost
  5. What does not need a warning
  6. When a warning leads to an event
  7. Related guides

Warn whenever you learn of something that might raise the Prices, push Completion back, endanger a Key Date or weaken how the finished works perform. Stating that is easy. Spotting a problem while it is still just a possibility is harder, so this guide offers a test and some examples. Clause numbers are NEC4 Engineering and Construction Contract (ECC) unless stated.

A four-question test

  1. Could it plausibly have one of those four effects? It need not be likely.
  2. Do I really know? The duty begins with awareness. A hunch merits a brief check, no more.
  3. Would they want time to respond? If staying quiet would embarrass you later, warn.
  4. Is it already a notified compensation event? Then the clause says nothing more is required.

Examples

Area Matter What it could affect Often raised by
Highways The lane closure booking may be withdrawn for the week planned Completion, Prices Contractor
Highways A statutory undertaker has postponed the cable diversion Key Date, Completion Either
Rail The signalling isolation you need may be moved to a later possession Key Date, Completion Either
Rail An approval for a substituted fixing is slow Completion, performance Contractor
Water The operator may refuse an outage on the trunk main Key Date, Prices Project Manager
Water A substitute pump curve gives less flow than designed Performance in use Contractor
Energy The network operator's connection date may slip Completion, Key Date Either
Buildings A cladding sample has no sign-off Completion Either
Any A maintenance regime means site users will restrict access Prices, Completion Project Manager

The Project Manager is the person the Client appoints to run the contract day to day. See the sector guides for highways, rail and water.

Easy to overlook

  • Your own problems. A late crew or a failing supplier can delay Completion, and you owe a warning even though the cost is yours. The Project Manager may be able to reshuffle other work to help.
  • Performance in use. A cheaper substitute might meet the date and still cost the operator more over its life.
  • What the Client knows first. Budget reviews, a new end user or a neighbouring scheme all count, and the Project Manager owes a warning on those.
  • Interfaces. Another contractor's programme can hit yours before anything on your own works has gone wrong.

The optional warning on your own cost

The Contractor may also warn of other matters that could raise its own total cost. A supplier's price increase on a fixed-price option is the classic case: without price adjustment it does not change the Prices, so the compulsory limb is not engaged, but you may still be hurt. A warning lets the Project Manager suggest a different specification or timing. It costs little and shows good faith, though the contract does not require it.

What does not need a warning

  • Anything you have already notified as a compensation event.
  • Anything that cannot affect the four items, such as moving a site cabin.
  • General hazards with no trigger. "It might rain" adds nothing, whereas "the forecast shows the haul road flooding next week" does. Long lists of every conceivable risk bury the ones that matter.

When a warning leads to an event

A warning often comes first. Suppose free-issue valves from the Client look set to land after the date shown in the Accepted Programme (the programme the Project Manager has accepted as your baseline). Warn at once, while the delivery can still be rescued. If the date is then missed, a distinct event arises under 60.1(3), and that needs its own notice.

This guide is general information, not legal advice. Check it against your contract.