Missed an NEC Key Date: what it can cost you and how to limit it
What clause 25.3 lets the Client recover when you miss a Key Date, how to test the Project Manager's figure and what to do while the date is still ahead.
On this page
A Key Date has gone by and the Project Manager is talking about what it has cost the Client. Before you assume the worst, know that the contract limits what can be charged.
The short answer
Missing a Key Date (a date in the Contract Data by which you must reach a stated condition, often so someone else can start) costs you only the additional cost the Client has paid or will incur because of it. Clause 25.3 gives no daily rate. Where the Client is no worse off in cash terms, the charge is nil, however late the date was missed. So the fight is about cause and evidence, and your first move is to record when you actually met the condition.
What to do, step by step
- If the date has not yet passed, warn now. Early warning clause 15.1 (16.1 in NEC3) covers a Key Date under threat. Others waiting to follow you can then rearrange before money is spent, which is your best lever on the final figure.
- Record the day you met the condition, with photographs and sign-off. The Project Manager's assessment runs from that date, so check the period in your own contract.
- Work out whether the fault was yours. An event that held you up should push the Key Date back (63.5). Any event not yet notified needs notice inside the eight-week limit from the moment you became aware (clause 61.3).
- Identify who was hit. Establish who was meant to follow you and the day they actually turned up.
- Ask for the build-up when the figure arrives, and test every line.
Testing the figure
| Question | Why it matters |
|---|---|
| Is it extra cost of doing the work, or an extra payment made to a third party (Others)? | The clause covers those two kinds only, tied to this project |
| Is it down to the missed condition? | A follower who was never ready cost the Client nothing through you |
| Has it been paid, or will it really be incurred? | A forecast is accepted if it has a basis |
| Is it lost rent or lost income? | Hard to fit within the clause, so ask how it qualifies |
| Did you really fail the wording of the condition? | The condition as written is tested, not how finished the work looked |
What to record
- Evidence of the date and time the condition was met.
- Who was due to follow you, and when they actually mobilised.
- Every notice and warning about the date, with delivery proof.
- The Client's invoices or contracts behind each line of the claimed cost.
What not to do
- Do not confuse a Key Date with delay damages. Option X7 sets a rate for late Completion and does not apply to Key Dates. A late Key Date does not by itself mean late Completion, and you face both only if both are separately missed.
- Do not stay silent about a coming miss. Under 61.5 a warning you never gave can cut the value of a related event.
- Do not let a figure you dispute pass unchallenged. Object in writing when it is certified, and check the dispute deadline for your form: with Option W1 a four-week clock starts when you become aware.
When to get help
Speak to your commercial manager as soon as a Key Date is forecast to be missed, and to a legal adviser if the claimed figure is large or includes lost income. A planner can show whether the miss came from your own work or from an event.
Example
On a pumping station refurbishment, the Key Date requires the valve chamber to be dry and lockable by 10 June so the Client's electrical contractor can start. You meet the condition on 24 June.
| Item put forward | Amount | Likely outcome |
|---|---|---|
| Electrical contractor's waiting time, paid by the Client | £12,000 | Stays, if its contract made the Client pay |
| Re-booking a crane | £2,500 | Stays, if the lift genuinely moved |
| Client's lost income from later start-up | £40,000 | Query: not obviously a work cost or sum paid to Others |
| Electricians' waiting time while they were on another site | £6,000 | Should come out |
Related guides
- Key Dates and sectional completion
- Delay damages
- Do I give an early warning when I notice a problem
- Time bars explained
This guide is general information, not legal advice. Check it against your contract.
