No accepted programme on an NEC job: how compensation events get assessed
What happens to time and money for a compensation event when the Project Manager has not accepted your programme, and how to fix the gap.
On this page
A compensation event has come up, and nobody has ever accepted your programme. You want to know whether you can still be paid and given more time, and who decides how much.
The short answer
You can still notify, quote and be assessed. What changes is who holds the pen on time. Under clause 64.2, with no accepted programme the Project Manager (the person the Client appoints to run the contract day to day) builds their own programme for the remaining work and measures the delay against that. Your quotation still matters, but your time claim now depends on someone else's picture of the job. The quickest cure is to get an accepted programme in place.
The same rule applies in NEC3 and NEC4. It also bites if you never submitted a programme you were required to, or if your latest one was turned down on a ground the contract recognises.
What to do, step by step
- Find out why there is no accepted programme. Check three things. Was a first programme due? Does the Contract Data (the part of the contract where project-specific figures are filled in) name one? Did the Project Manager ever reply? The fix differs for each.
- Submit a compliant programme now if nothing has gone in. Include everything clause 31.2 lists. If the Project Manager is silent, chase: they have two weeks to respond under 31.3.
- On NEC4, use deemed acceptance. Tell the Project Manager in writing that their reply is overdue. A further week of silence and the programme counts as accepted. NEC3 has no equivalent, but a late reply there can be a compensation event under 60.1(6).
- Keep notifying events. The eight-week limit in 61.3 does not pause because the programme is missing (seven weeks under the NEC4 subcontract).
- Quote anyway, and attach your own programme. It may be overruled, but it puts your plan on the record and gives the Project Manager a starting point.
- Watch the Project Manager's timing. Under 64.3 they have the same period you had to quote (three weeks in the NEC4 main contract). If they miss it, notify the failure: after another two weeks your quotation is treated as accepted (64.4).
What changes without an accepted programme
| Point | With one | Without one |
|---|---|---|
| Measuring delay | Planned Completion on your programme at the dividing date (63.5) | The Project Manager's own programme (64.2) |
| Who assesses | You quote, they reply (62.3) | They may step in and assess (64.1) |
| Late access events | Later of the Contract Data date and the programme date | Only the Contract Data date is left to test |
| Payment | Unaffected | Where the Contract Data names none, a quarter of each Price for Work Done to Date assessment is withheld until a compliant first programme arrives (50.5; NEC3 50.3) |
What to record
- When each programme was submitted, and the reply or lack of one.
- The stated reason for any rejection, and whether it is one the contract allows.
- Your progress records, so a progress survey by the Project Manager can be tested.
- Your own programme version attached to every quotation.
What not to do
- Do not hold back a notice because the programme is missing.
- Do not accept a Project Manager's programme that carries your own earlier slippage without challenging it.
- Do not treat the quarter retention in payment as a mere admin point.
- Do not let a rejection for an invented reason pass. If the reason is not one in 31.3, the refusal may itself be a compensation event.
When to get help
Get a planner involved as soon as a quotation depends on time, because baseline logic wins or loses the argument. Involve a commercial manager or legal adviser when an assessment looks well below your own and the sums are large.
Example
A pumping station refurbishment on Option C has no programme named in the Contract Data. The contractor's first programme was rejected in February for missing resources and nothing has been accepted by June. In June the Project Manager instructs an extra chlorine room. The contractor quotes £95,000 and five weeks with its own programme. The Project Manager assesses instead, builds a programme from a progress survey, and finds the room adds only three weeks, because the survey shows earlier slippage on a parallel activity. Had a programme been accepted in February, the five weeks would have been measured from the contractor's own plan.
Related guides
- What the accepted programme is
- Deemed acceptance of a programme
- PM has not accepted my programme
- Using the programme to assess compensation events
This guide is general information, not legal advice. Check it against your contract.