Your duties as the NEC Contractor, and the ones that quietly cost money

A working list of what the Contractor must do under the NEC4 ECC, grouped by build, time, quality and notices, with a pre-start checklist.

NEC basics for newcomers4 min read

On this page
  1. Building and design
  2. Time
  3. Quality and Defects
  4. Notices, quotations and money
  5. Mistakes to avoid
  6. Before you start
  7. Related guides

Your main duty under NEC is simple: Provide the Works in line with the Scope (20.1). Around it sit many process duties, from early warnings to programmes, quotations and Defects. Miss some and you lose money even when the building work is perfect. The clauses here are from the NEC4 Engineering and Construction Contract (ECC). Under NEC3 the Scope is called Works Information, and a few numbers differ.

Building and design

  • Design what the Scope says you design, and submit particulars for acceptance before going ahead (21.1, 21.2).
  • Supply the key people named in the contract, or an accepted substitute, and take someone off the job if instructed with reasons (24.1, 24.2).
  • Work alongside Others in the Working Areas in the way the Scope describes (25.1), and supply whatever the Scope says you will (25.2).
  • Stay responsible for subcontracted work (26.1), and submit each proposed Subcontractor for acceptance, with subcontract documents where required (26.2, 26.3).
  • Obtain any approvals your design needs from Others (27.1), give access to those named (27.2), obey permitted instructions (27.3) and meet the health and safety rules the Scope sets out (27.4).

Time

  • Reach Completion no later than the Completion Date (30.1) and meet each Key Date condition (30.3). Missing one that costs the Client extra can mean you pay the assessed difference (25.3).
  • If the Contract Data names no first programme, submit one within the stated period, showing what 31.2 asks for (31.1).
  • Send in revised programmes when asked and at the regular intervals fixed in Contract Data (32.2).

An unaccepted programme causes real harm. Part of your payment can be held back (50.5), and the Project Manager can step in and assess compensation events itself (64.1).

Quality and Defects

  1. Operate your quality system, and submit the policy statement and plan for acceptance (40.1, 40.2).
  2. Give enough notice for tests to take place before work is covered (41.3).
  3. Keep Plant and Materials that need testing out of the Working Areas until they pass (42.1).
  4. Search for a Defect if instructed (43.1) and notify any you find, up to the defects date (43.2).
  5. Correct Defects whether notified or not (44.1), and fix each notified one inside its defect correction period (44.2).

Notices, quotations and money

Duty Clause Why it matters
Give an early warning once you are aware of a risk 15.1 Without one, a linked compensation event can be assessed as though you had given it (61.5, 63.7)
Go to early warning meetings you are called to 15.2 Gives shared solutions and a record
Notify ambiguities or inconsistencies 17.1 The Project Manager then says how to resolve them
Notify a compensation event the Project Manager has missed, inside eight weeks of first becoming aware 61.3 Late notice may cost you the change, with limited exceptions
Send your quotation within three weeks 62.3 If you miss it, the Project Manager may assess instead
Submit a payment application ahead of each assessment date 50.2 An NEC4 addition
Take out the insurance required and hand over certificates for acceptance 84.1 Due before the starting date

Both sides are also bound to act as the contract says (10.1) and to work in mutual trust and co-operation (10.2). Your liabilities sit in section 8.

Mistakes to avoid

  • Waiting for the Project Manager to notify. If they should have and have not, you can still notify. Do not assume someone else is tracking it.
  • Treating acceptance as a shield. Their acceptance of your design leaves your design liability intact (14.1).
  • Building on unaccepted design. Chase the reply, and note that a late one may itself be a compensation event.
  • Pricing the money but forgetting the days. Your quotation has to cover any delay too, supported by an updated programme where needed (62.2).

Before you start

  1. Go through the Scope and Contract Data with the people who will build the job as well as the commercial staff.
  2. List every periodic duty in a shared diary.
  3. Confirm key people and a plan if one leaves, and prepare subcontractor submissions early.
  4. Flow obligations into subcontracts with periods short enough to fit yours.
  5. Have insurance certificates ready and registers set up for early warnings, compensation events and Defects.

This guide is general information, not legal advice. Check it against your contract.