Your first NEC programme: when it is due and how the 25% deduction works

When to submit your first NEC programme under clause 31.1, what ends the 25% payment deduction, and a practical order of work for getting it in.

Programmes and time3 min read

On this page
  1. In plain English
  2. Do you need one at all?
  3. What the deduction really says
  4. Example
  5. Other costs of not having one
  6. A practical order of work
  7. Related guides

Your first programme is the plan you send the Project Manager (the person the Client appoints to run the contract) for acceptance under clause 31.1, within the period stated in the Contract Data. Until you have sent one that shows what the contract requires, every payment assessment takes 25% off the Price for Work Done to Date, which is the value of work done so far.

The rule is the same in NEC3 and NEC4 ECC, though the clause moved: it is 50.5 in NEC4 and 50.3 in NEC3. How you handle this sets the tone for the rest of the job.

In plain English

Get a complete first programme in early. Sending it, not having it accepted, is what stops the deduction, but only if it contains everything required.

Do you need one at all?

  • The Contract Data names a programme. That programme is the Accepted Programme from day one. Clause 31.1 does not apply and neither does the deduction. Your next submission is a revision under clause 32.
  • No programme is named and a period is given. You must submit within that period. Check where the period starts: in subcontract data it can run from the Subcontract Date, so read your own form.

A named programme looks convenient, but it carries risk for the Client: tender programmes seldom show everything, and this one becomes the Accepted Programme without the review that 31.3 provides. If you are the one proposing it, check it before signing exactly as you would check a formal submission. The Contract Data guide shows where these entries sit.

What the deduction really says

People describe it as money held until the programme is accepted. The clause is narrower.

  1. Submission is the trigger. Once you have put forward a first programme for acceptance that contains the required information, the deduction ends.
  2. The content must be there. A partial programme missing required items does not end it.
  3. It bites on one figure. It comes off the Price for Work Done to Date only, not the whole amount due.

So a programme can end the deduction even if the Project Manager refuses it for some other reason, such as an impracticable plan. See the Price for Work Done to Date for what the percentage is applied to.

Example

Invented figures for a culvert replacement.

Assessment Price for Work Done to Date Position Held back
Month 1 £80,000 Nothing submitted yet £20,000
Month 2 £200,000 Submitted, but a required item missing £50,000
Month 3 £330,000 Resubmitted complete; Project Manager queries sequencing £0

The wording looks at whether you have submitted, not at whether the Contract Data period has expired, so the deduction can apply in month 1 before the programme is even due. That is a reason to be early. Once it ends, the money is not lost: later assessments simply stop deducting it.

Other costs of not having one

  • The Project Manager takes over pricing. If no first programme has gone in when an event is quoted, they can do the assessment themselves (64.1), working from their own idea of the programme (64.2).
  • Nothing to hold the Client to. With no accepted dates, you cannot point to the programme for access or Client-supplied items.
  • Early arguments. Without a baseline, every event in the first months becomes a debate over what was planned.

A practical order of work

  1. Read the Contract Data entries and the Scope requirements, including the required format under NEC4.
  2. Start from the tender programme, then update for pre-construction changes and supplier dates.
  3. Check it against every item in clause 31.2.
  4. Walk the Project Manager through a draft if you can. It is not required, but it often avoids a formal refusal. Make clear the draft is not the submission.
  5. Submit formally, naming it the first programme under 31.1, and record the date. The Project Manager then has two weeks to reply.

This guide is general information, not legal advice. Check it against your contract.

Was this useful?