NEC payment mistakes that cost contractors money
The payment errors that most often cost NEC contractors and subcontractors cash, grouped by stage, each with a practical fix.
On this page
Payment on an NEC contract is run by dates and by evidence. Nearly every loss traces back to a deadline that passed unnoticed, a defined term read the wrong way, or paperwork that nobody kept. Each date has its own consequence, so a small slip can turn into a lot of money. Examples below use NEC4 and the Engineering and Construction Contract unless stated.
At the start of the job
- No first programme in. If the Contract Data does not identify one and you have not submitted it, the Project Manager (the person the Client appoints to run the contract day to day) can hold back a quarter of the value of work done under clause 50.5. Have the programme ready before the first assessment date.
- First assessment date never confirmed. You cannot plan an application around a date nobody has stated. Ask for it in writing.
- Printed periods used instead of your Contract Data. Teams often work to the standard weeks they remember. Put the real dates in a calendar from week one.
- Vague Activity Schedule entries. If two people read "complete" differently, you will argue every month. Settle a clear finish point for each activity at tender.
Every payment cycle
- A late application. Under NEC4 clause 50.4, if you apply on or after the assessment date, the amount due cannot rise. Give yourself an internal deadline a few days earlier.
- Certificate and invoice confused. Some Clients need a separate invoice. Agree early who sends what, or finance may sit waiting.
- Interest counted from the wrong day. Clause 51.2 runs from the assessment date, not the day the certificate arrived.
- A negative certificate not spotted. Check which way the money flows, not only the size of the number.
- A badly worded pay less notice. Saying "we deduct £X" misses the point. The notice should state the sum now considered due and show the working.
- A missed pay less deadline. The certified sum then generally has to be paid. Read each certificate within days of receipt.
- Relying on next month's correction. Putting a mistake right later does not reduce this month's payment. A notice does.
On target and cost-reimbursable Options
- Internal cost reports treated as Defined Cost. Your management report is not organised the way the schedule is. Keep a separate view by schedule section.
- Payment not proven. Cost your records do not justify can be struck out, and the Fee on it goes too. Tie bank records to ledger lines.
- Own-group plant at internal rates. The schedule points to open market rates, so collect evidence when the plant arrives.
- Full-time charging of a shared manager. Only the proportion working in the Working Areas is allowed. Keep time records.
- Rebates forgotten. Clause 52.1 deducts them, even after you were paid. Ask your finance team for a list every quarter.
- Forecasts that drift upward. Test each forecast against what actually happened, or credibility drains away.
Closing out
- Open compensation events left to the end. They get harder to agree and the final deadline does not move. Clear them in batches during the defects period.
- The 53.3 challenge window missed. Diary four weeks from the day the final assessment is issued.
- Second half of retention not checked. It does not release itself. Look for it in each later assessment.
- Delay damages not recalculated. After an implemented event moves the Completion Date, any overpayment returns with interest under X7.2.
A quick monthly check
- What are the actual dates of the next application, certificate, pay less deadline and final payment date?
- Does the certificate reconcile to your application line by line?
- Has anything changed this month in the Prices, the Completion Date or retention?
One named person should own a shared tracker that answers these questions.
In plain English
Know your dates, keep proof of what you paid, and read every certificate promptly. Most payment disputes start with one of those three slipping.
Related guides
- Making an NEC payment application
- Pay less notices under NEC
- Retention under NEC
- The final assessment
This guide is general information, not legal advice. Check it against your contract.