NEC assessment dates: when your payment is worked out
How assessment dates and the assessment interval set your payment cycle, who chooses the first one, and how to avoid losing a month's cash.
On this page
Every payment on an NEC contract hangs off one date: the assessment date. It is the day the amount due is worked out, and the certificate, the payment and any interest are all counted from it. If you work out when yours fall, you know when to apply, when cash arrives and what a slipped day costs.
Clause 50.1 sets this out in both NEC3 and NEC4. The Project Manager (the person the Client appoints to run the contract day to day) picks the first assessment date. After that, the assessment interval, a figure in the Contract Data (the part of the contract where the project-specific numbers are filled in), decides the rest.
How the dates are fixed
| Point | What applies |
|---|---|
| First date | Chosen by the Project Manager, who is meant to consider both sides' own payment routines |
| Latest it can be | One assessment interval after the starting date |
| Later dates | One interval after the last, repeating |
| End of the run (NEC4) | Until a termination certificate or the Defects Certificate is issued |
| End of the run (NEC3) | Four weeks after the Defects Certificate, with one extra date when the whole of the works reaches Completion |
Some Options add extra dates. With the delay damages Option (X7), the day any overpaid damages are repaid also counts as an assessment date.
Weeks or months?
The NEC3 Contract Data asks for an interval in weeks, with an upper limit of five. Many finance teams prefer calendar months. If your contract says weeks, a monthly cycle needs a clear entry or an extra Z clause (a project-specific amendment). Otherwise your accounts team and the contract quietly disagree.
- A four-week cycle gives thirteen dates a year, and the date drifts through the calendar.
- A calendar-month cycle gives twelve and sits neatly with a month-end close, but only if it has been properly agreed.
Read the interval in your own Contract Data before you set up the finance diary.
Why a single day matters
Picture a pipe-laying subcontractor on a fictional water job. A £150,000 section finishes on the 14th. With an assessment date on the 13th, that section waits for the next cycle, roughly four weeks away. With the date on the 15th, it is paid in this one. The delay in cash is yours to carry.
Under NEC4 you also have to send your application in before the assessment date, so you are applying for work you expect to be finished by then. The Project Manager then assesses the position as it stands on the day.
Settling the first date sensibly
Raise it at the kick-off meeting. Useful questions to put:
- When does the Client run payments? Ideally the final payment date lands just after a run.
- When does your own cost ledger close? On cost-reimbursable and target contracts the application depends on it.
- When are your subcontractors' assessment dates? You usually need their figures before you can apply upward.
- Do any dates fall around Christmas or bank holidays?
What people get wrong
- Never getting the first date confirmed. If nobody states it, the latest possible date still applies, but you cannot plan your application. Ask in writing.
- Moving the date to relieve a cash shortage. Once the first date is set, the interval decides. Changing it needs a real agreement between both sides.
- Expecting weekends to shift it. The contract says nothing of the kind. Put the actual day in the diary and agree in advance how a non-working day will be handled.
- Thinking dates stop at Completion. They keep running, so retention and final sums can be dealt with.
In plain English
The assessment date is the day your payment is calculated, and every other payment deadline counts from it. Get it confirmed early, put it in everyone's diary, and treat a one-day slip as a possible month of lost cash.
Related guides
- The NEC payment timeline
- Making an NEC payment application
- How payment works under NEC
- Running an NEC kick-off meeting
This guide is general information, not legal advice. Check it against your contract.