Price for Work Done to Date: the figure your NEC payment starts from
How the Price for Work Done to Date is worked out on each NEC main Option, why Options A and B reward finished activities, and why C, D and E use a forecast.
On this page
Price for Work Done to Date, often shortened to PWDD, is the main figure in every NEC assessment of what you are owed. Where your contract is Option A or B, it counts finished work at the Prices. Where it is C, D or E, it is a forecast of cost plus the Fee, so it says nothing directly about progress. Knowing which one your contract uses explains why your cash flow behaves the way it does.
How each main Option defines it
- Option A: the total of the Prices for activities and groups of activities that are complete (NEC4 11.2(29), NEC3 11.2(27)).
- Option B: completed quantities at the rates, plus the finished share of each lump sum (NEC3 11.2(28); in NEC4 it is in 11.2, so check your copy).
- Options C, D and E: the Defined Cost the Project Manager expects to have been paid by the next assessment date, plus the Fee (NEC4 11.2(31), NEC3 11.2(29)).
- Option F: the same approach, using Option F's own Defined Cost (NEC3 11.2(29); check your NEC4 copy).
The Project Manager is the person the Client appoints to run the contract day to day. Defined Cost is the cost you actually incur, as the contract defines it.
Options A and B: finished or not
On Option A an activity is complete or it is not. There is no percentage complete. It counts as complete when no notified Defect would, once corrected, delay the work that follows. So:
- A minor snag that holds nobody up does not stop payment.
- A failed pour that sits under the next trade's work does hold it up, even if the activity looks done.
- An activity that is 95% done pays nothing.
This is why breaking the Activity Schedule into smaller pieces helps cash flow. Option A also lets activities be grouped, with nothing paid until the whole group finishes, so read any groupings carefully. Option B applies the same test to quantities, while lump sum items in the bill can be paid in proportion.
Example. A retaining wall on Option A has three activities: piling £50,000, capping beam £30,000, wall panels £90,000. Piling is finished. The capping beam is cast, but a notified Defect means it must be recast before panels can be fixed, and the panels are half done. PWDD is £50,000, however much has been spent.
Options C, D and E: a forecast
Here the Project Manager looks forward, not back. They estimate what you will have paid out by the next assessment date, so each assessment reaches up to one interval ahead and keeps you in funds.
| Illustrative Option C assessment | £ |
|---|---|
| Defined Cost paid to date, from records | 500,000 |
| Forecast to be paid before the next assessment date | 80,000 |
| Disallowed Cost identified | (10,000) |
| Total Defined Cost | 570,000 |
| Fee at 5% | 28,500 |
| PWDD | 598,500 |
Next time the forecast is replaced by actual figures and a new one added, so errors correct themselves. A consistently high forecast is still worth raising, since it may put you in funds ahead of need.
Where the figure goes
- It is the first line of the amount due under clause 50.
- It determines when retention under X16 starts, since it has to exceed the free amount first.
- If Contract Data names no first programme and none has been submitted, a quarter of it is withheld under 50.5 in NEC4 (50.3 in NEC3).
- On Options C and D, the final figure is set against the Prices to produce the share (clause 54 in NEC4, 53 in NEC3).
What people get wrong
- Using percentage complete on Option C. It helps management but is not the contract test.
- Believing it is the whole payment. Retention, delay damages and other items are separate lines.
- Treating "certified to date" as the same thing. The certificate reports the change in the amount due, and the two diverge once other items come in.
Related guides
- How payment works under NEC
- The Activity Schedule
- Target cost and the Contractor's share
- Making an NEC payment application
This guide is general information, not legal advice. Check it against your contract.