How to submit an NEC payment application

What to put in an NEC4 payment application, what happens if you send it late, and a checklist to use before every submission.

Payment and cost3 min read

On this page
  1. What the application is built from
  2. Before you press send
  3. Example: a fictional bridge-bearing job
  4. If you miss the date
  5. What not to do
  6. In plain English
  7. Related guides

If you are the contractor or subcontractor on an NEC4 contract, you have to send in an application for payment before each assessment date. Send it late and you lose the ability to raise your amount for that cycle. This guide covers what to include and how to avoid that trap.

Under clause 50.2 of NEC4, your application is a statement of the amount you think is due at the next assessment date (the date the payment is worked out), with the working behind it. NEC3 did not require one: the Project Manager, the person the Client appoints to run the contract day to day, simply looked at any that arrived on time.

What the application is built from

The core calculation depends on your main Option, the pricing method chosen for the contract.

Option Core figure Backing you should attach
A Activities marked complete on the Activity Schedule Evidence of completion, and any Defects affecting later work
B Measured quantities at the bill rates, plus part-completed lump sums Measurement records and sketches
C and D Defined Cost paid so far, plus what you forecast to pay before the next date, plus the Fee Cost ledger by schedule section, forecast build-up, subcontract account summaries, current view of the target
E As C and D, without a target As C and D

Every Option then adds the same lower lines: other sums due to you, retention, delay damages and anything else payable by you. Clause 50 gives the full make-up of the amount due.

Before you press send

  • Is it going in ahead of the assessment date, by the route the contract requires for communications?
  • Does it follow any format the Scope (the document describing the work) asks for?
  • Does it show the position at the assessment date, including work you expect to finish by then?
  • Have compensation events that have been implemented been added, with the updated Activity Schedule?
  • Have you carried forward any earlier correction?
  • Are the lines for secondary Options such as X7 (delay damages), X14 (advanced payment) and X16 (retention) included where they apply?
  • Is a first programme in? If not, expect a quarter of the value of work done to be held back under clause 50.5.
  • Can a reader reconcile it to the last application at a glance?

Example: a fictional bridge-bearing job

An Option A subcontract package, simplified:

Line £
Completed activities 380,000
Completed activities from implemented compensation events 20,000
Price for Work Done to Date 400,000
Retention, 5% above a £100,000 free amount (15,000)
Amount you consider due 385,000
Amount due last time (300,000)
Movement this period 85,000

The detail sits behind this page in the attachments, so the Project Manager can follow it in a minute.

If you miss the date

Clause 50.4 says the amount due becomes the lower of the Project Manager's own assessment and the amount due last time. It cannot go up. What you left out is not lost, because you can claim it in the next application, but you may go a full interval without it. Tell your site and commercial teams that a late application costs real money.

What not to do

  • Do not slip in unagreed claims as though they were settled. If you believe a compensation event is owed, list it separately. An unsupported figure weakens the rest of the application.
  • Do not treat the application as a notice. Compensation events need their own notification. Mentioning one in a payment application is not a safe substitute.
  • Do not inflate forecasts on cost-based Options. They get compared with reality next month and credibility suffers.
  • Do not confuse it with a VAT invoice. Many Clients want one as well, usually after the certificate. Check for a Z clause.

In plain English

An application is your own sum of what you are owed, sent before the payment date, with proof. If it is late, your number cannot rise for that cycle.

This guide is general information, not legal advice. Check it against your contract.