How NEC subcontractors get paid: periods, dates and cash flow

The certification and payment periods in the NEC Engineering and Construction Subcontract, lining them up with the main contract, and late payment.

Payment and cost3 min read

On this page
  1. Main contract and subcontract compared
  2. Fitting your dates to the main contract
  3. Fair payment points
  4. Retention
  5. Example: a drainage subcontractor paid late
  6. What subcontractors often miss
  7. In plain English
  8. Related guides

If you work under the NEC Engineering and Construction Subcontract (ECS), you wait longer than the main contractor does. The Contractor must certify within two weeks of each assessment date, and payment should follow within four weeks, unless your Subcontract Data (the project-specific figures) gives a different period. Those periods are the same in NEC3 and NEC4.

The short subcontract form uses a different system, so check which form you have.

Main contract and subcontract compared

Step Main contract (ECC) Subcontract (ECS)
Who assesses and certifies Project Manager The Contractor
Who applies (NEC4) Contractor, ahead of assessment date You, ahead of assessment date
Certificate issued Within 1 week Within 2 weeks
Payment Within 3 weeks Within 4 weeks
Option Y(UK)2 due date 7 days after assessment 14 days after
Final date for payment 14 days after due date 14 days after due date
Pay less notice (Y2.3) 7 days before final date 7 days before final date

If you apply late, clause 50.4 applies exactly as in the main contract: your amount due cannot go above the previous one.

Fitting your dates to the main contract

The Contractor picks your first assessment date. A sensible pattern puts the subcontract date a few days ahead of the main contract date, so your figures can feed the Contractor's own application upward. With day 0 as the main contract assessment date, it might run:

  1. Day -8: you submit your application.
  2. Day -7: subcontract assessment date.
  3. Day -1: Contractor applies upward.
  4. Day 0: main contract assessment date.
  5. Day 7: main certificate, and your own two-week certificate comes within this window.
  6. Day 21: Client's payment due and your four-week date.

Under this pattern the Contractor receives and pays at about the same time. Reverse the order and it may be funding you before it has been paid, which is why many main contractors resist it. Look at your own package closely before pricing the cash flow.

Fair payment points

  • Pay when paid. The Construction Act generally stops a contract making your payment depend on the Client paying the Contractor, apart from a narrow case involving upstream insolvency. A main contractor normally cannot withhold simply because it has not been paid, unless a valid pay less notice rests on another reason.
  • Public work. Procurement rules and many Clients' Scope or Z clauses set shorter payment periods down the chain, often 30 days. Check both what your subcontract says and what the main contract passes down.
  • Project bank accounts. Option Y(UK)1 allows named suppliers to be paid straight from a project account.
  • Longer periods. The Subcontract Data can lengthen the printed period, so read it before tender.

Retention

Option X16 in the subcontract has its own free amount and percentage. Under NEC4, a retention bond can be offered instead if the data allows or the Contractor agrees.

Example: a drainage subcontractor paid late

A fictional NEC4 package: certified £80,000, annual interest of 5% in the Subcontract Data. Payment lands 20 days after the final date and no pay less notice was given.

  • Interest: £80,000 x 5% x 20 / 365, about £219, added in the next assessment.
  • With Y(UK)2, a properly exercised statutory right to suspend is a compensation event. Take advice first, because notice is required.
  • You can also refer the debt to adjudication through your dispute Option.

What subcontractors often miss

  • Your data may state a payment period other than four weeks.
  • The NEC4 subcontract has its own final assessment clause (53.1), with different dates from the main contract. Diarise them separately.
  • Your application must follow any format in the Subcontract Scope.

In plain English

You are assessed and paid on the same pattern as the main contractor, but later. Know your Subcontract Data periods and check the cash gap before you commit.

This guide is general information, not legal advice. Check it against your contract.