The NEC payment cycle in days: from assessment date to money in the bank
A day-by-day view of the standard NEC4 payment cycle for main contracts and subcontracts, with a dated example and the holiday traps.
On this page
On a standard NEC4 main contract with Option Y(UK)2 (the secondary option that brings in the UK Construction Act payment rules), money should arrive 21 days after each assessment date. The certificate and due date fall by day 7, any pay less notice must be in by day 14, and day 21 is when payment is finally due. The payment period is an entry in Contract Data and a Z clause (an added condition) may alter other steps. Use this as a template and overwrite it with your own dates at the start of the job.
The main contract, day by day
- Before day 0: you submit your application for payment (50.2).
- Day 0, the assessment date: the Project Manager, the person the Client appoints to run the contract, assesses the amount due (50.1).
- By day 7: payment certificate issued, which doubles as the payment notice under Y(UK)2 (51.1, Y2.2). Payment also becomes due.
- Day 14: the last day for a pay less notice (Y2.3), from whichever party intends to pay less.
- Day 21: the final date for payment (51.2, Y2.2).
- Next cycle: interest on late payment is picked up in the next assessment (51.2).

Without Y(UK)2 the contract itself only has the certificate and payment steps, though the Construction Act generally applies anyway on UK construction work.
If you are a subcontractor
On the NEC subcontract (ECS) each step is a week later: the certificate comes within two weeks, payment falls due 14 days after the assessment date, the last pay less notice is day 21, and the final date for payment is day 28. Both sets are the printed figures, and a payment period entry in Contract Data or Subcontract Data can change them. Ask your main contractor which version it is working to.

A dated example
Take an invented contract with a monthly-style four-week interval and an assessment date of Friday 9 May, with no bank holidays nearby.
- 8 May: latest date for your application.
- 9 May: assessment date.
- 16 May: certificate issued and payment due.
- 23 May: last day for a pay less notice.
- 30 May: final date for payment.
- 6 June: the following assessment date; your next application goes in on 5 June.
Notice how soon the next application follows payment. The cycles overlap, so a QS is usually finishing one while preparing the next.
Days, weeks and holidays
Periods in days under Y(UK)2 are counted specially. The NEC4 subcontract's Y2.1 skips Christmas Day, Good Friday and bank holidays, whereas NEC3 Y2.1 points to the Act's method. Core clause periods are in weeks with no such skipping. Over Christmas or Easter the two dates can therefore split, so plot both and work to the earlier.
Before the first cycle
- Get the first assessment date confirmed in writing. It cannot be later than one interval after the starting date.
- Read the Contract Data entries for payment period, interval and interest rate.
- Check for a Z clause on invoicing. Many Clients add steps, such as needing a VAT invoice before they pay.
- Agree in advance who on the Client side may issue a pay less notice.
- Put the whole job's calendar in place now. It is far easier done once.
Related guides
- How payment works under NEC
- Pay less notices under NEC
- Assessment date and assessment interval
- Payment for NEC subcontractors
This guide is general information, not legal advice. Check it against your contract.