Subcontractor delayed by the main contractor or other trades

What an NEC subcontractor should do when late access, other trades or the main contractor's delays stop you working, and how to protect time and cost.

Subcontractors and supply chainScenario3 min read

On this page
  1. The short answer
  2. What to do, step by step
  3. What to record
  4. What not to do
  5. When to get help
  6. Example
  7. Related guides

You turned up as planned and could not work. The area was not ready, another trade was still in it, or the main contractor moved the sequence. Your programme is slipping and you are being asked to hold the original finish date. This guide is for the Subcontractor.

The short answer

Tell the Contractor in writing the same day, record exactly what stopped you, and notify a compensation event and early warning within the periods in your own subcontract. Late access, or the Contractor not providing something it should, is often a compensation event under NEC. If you do not notify in time, you may lose the entitlement to extra time or money.

What to do, step by step

  1. Record the stoppage on the day. Time, place, what was in the way, who was told.
  2. Give an early warning to the Contractor. Describe the problem and the effect on your dates and cost. See noticed a problem, do I give early warning.
  3. Check your subcontract for the relevant event. Look at the list of compensation events in your subcontract. Late access to the Working Areas, a failure to provide something by the date in the programme, and instructions that change sequence are common ones. Check the exact wording in your contract and Contract Data. For the main-contract version see late access to site.
  4. Notify the event in writing within your period. Under the unamended NEC4 subcontract (ECS), clause 61.3 gives you seven weeks from becoming aware, not the eight weeks of the main ECC. Check your Subcontract Data and Z clauses, because the periods can be amended. See time bars for subcontractors.
  5. Show the effect on your programme. Update your programme to show the delay and the effect on later work. Use your Accepted Programme as the baseline, or the programme the contract requires you to use. See delay analysis basics.
  6. Submit your quotation with the cost of standing time, remobilisation and re-sequencing, and any delay to your Subcontract Completion Date or Key Dates. Under the unamended NEC4 ECS you have two weeks to quote once instructed to, and the Contractor has four weeks to reply to the quotation.
  7. Mitigate. Redeploy gangs where you reasonably can and show what you did. Failure to mitigate can reduce what you recover.
  8. Keep the Contractor updated at each progress meeting, in writing, until the issue is closed.

What to record

  • Daily records of labour and plant on site and what they were doing, or not doing.
  • Photos showing the blocked or unready area, with dates.
  • Copies of the Contractor's programme and any look-ahead that shows the other trade's dates.
  • Instructions given on site to change sequence or move to another area.
  • Standing time, demobilisation and remobilisation costs.
  • Meeting minutes where the delay was discussed.

See keeping records under NEC.

What not to do

  • Do not wait until the end of the job to raise it.
  • Do not rely on "everyone knows we were held up".
  • Do not blame the Contractor in general terms. Name the event, the date and the effect.
  • Do not stop updating your programme because it looks bad.
  • Do not hide the effect of your own earlier slippage. Delay analysis will find it.

When to get help

Ask a planner to help once the delay affects your Completion Date or Key Dates, or when several delays overlap. Talk to your commercial manager before you submit a quotation. Take legal advice if the Contractor denies any responsibility and you are considering a dispute.

Example

A mechanical subcontractor is due to start installing plant in a chamber. On the day, the structural trade is still working in it. The Subcontractor emails the Contractor at once with photos, issues an early warning, and notifies a compensation event within its subcontract period. Five working days pass before access. The quotation covers standing time, the move to another area, and a five-day extension to its Key Date, supported by an updated programme.

This guide is general information, not legal advice. Check it against your contract.