Subcontractor not paid by the main contractor: what to do

What an NEC subcontractor should do when the main contractor has not paid, including pay-when-paid, interest and Construction Act rights in general terms.

Subcontractors and supply chainScenario4 min read

On this page
  1. The short answer
  2. What to do, step by step
  3. What to record
  4. What not to do
  5. When to get help
  6. Example
  7. Related guides

You have done the work, the payment date has passed and the money has not arrived. The main contractor says they are waiting to be paid by the Client. This guide is written for the Subcontractor.

The short answer

Check your own subcontract's payment dates first, then write to the Contractor chasing the sum due. In most UK construction contracts, a Contractor cannot rely on "we have not been paid by the Client" as a reason not to pay you. Pay-when-paid clauses are generally unenforceable under the Construction Act, with narrow exceptions such as the paying party's insolvency. Take legal advice before you rely on either view.

What to do, step by step

  1. Find your payment timetable. Look at the subcontract and Contract Data for the assessment date, the date payment is due, and the final date for payment. These are your dates, not the main contract's. In the NEC subcontract the Contractor certifies within two weeks of each assessment date and pays within four weeks, unless the Subcontract Data says otherwise. With Option Y(UK)2 and the standard periods the due date is 14 days after the assessment date and the final date for payment is 28 days after it, with the last day for a pay less notice seven days before that. How payment works in outline is in how payment works under NEC.
  2. Check what you applied for and what was assessed. Work out whether the issue is no payment at all, a late payment, or a payment less than you expected.
  3. Look for a payment notice or a pay less notice. Under the Construction Act, in general terms, the paying party must give notices if the amount is to be reduced. With Option Y(UK)2 the notice must state the sum considered due and its basis, and must be given at least seven days before the final date for payment. Without one, the notified sum is generally payable in full. Check whether you received them, when, and what they say. If none arrived, note it carefully.
  4. Write a clear chase. State the application, the sum, the date it fell due, and that it is unpaid. Ask for payment by a specific date and refer to interest for late payment as the contract provides.
  5. Escalate inside the Contractor. Copy the commercial manager and the person who signs payments.
  6. Claim interest on the late amount in line with your subcontract. Interest runs daily at the rate in the Subcontract Data, compounded annually, and is added to the first assessment after the late payment is made.
  7. Consider your statutory rights. Depending on your contract and the Construction Act, you may be able to suspend work after giving the notice required (at least seven days' written notice of your intention). With Option Y(UK)2 a proper suspension is a compensation event, which you must notify within eight weeks. You may also refer the dispute to adjudication. Both have strict steps and consequences. See adjudication under NEC and take legal advice before you do either.
  8. Keep working unless you have a clear right not to. Walking off site in breach can hand the Contractor a counterclaim.

What to record

  • Every application, with date and method of submission.
  • Any payment notice, pay less notice or assessment you receive.
  • Dates of every chase and the replies.
  • The value of work and materials, with measurements and photographs.
  • Evidence the work was accepted or used.
  • Any statement that the Contractor is "waiting for the Client".

What not to do

  • Do not accept "we have not been paid yet" as the end of the conversation.
  • Do not stop work without taking advice on notice and consequences.
  • Do not send aggressive messages. Stay factual.
  • Do not agree to a reduced sum informally without writing down what it covers.
  • Do not ignore your own application dates. A late or defective application can weaken your position.

When to get help

Get your commercial manager involved as soon as a payment is missed. Take legal advice before you issue a suspension notice, start adjudication, or rely on any argument about pay-when-paid. Ask a planner to help if the Contractor is saying you were late, or that delay by you has reduced what is due, because the answer sits in the programme records.

See also I have not been paid on time for the main contract version of this problem.

Example

A groundworks subcontractor submits an application, and payment is due on the date its subcontract gives. The date passes. The Subcontractor emails the Contractor: application date, the sum, the due date, a request for payment within five working days and a note that interest will be claimed. It copies the commercial manager. It gets a reply that the Client has not paid. It replies politely that its subcontract does not make payment depend on that, and asks for the payment notice or a pay less notice, if one was issued. It takes legal advice on the next step.

This guide is general information, not legal advice. Check it against your contract.