Open book on NEC cost contracts: the records you must keep

What open book means on NEC Options C, D and E, which records clause 52.2 expects, and how to set up cost codes and monthly reporting.

Payment and cost3 min read

On this page
  1. What changes for your team
  2. The records
  3. A cost code structure that works
  4. Monthly reporting
  5. Where teams go wrong
  6. In plain English
  7. Related guides

On NEC Options C, D and E you get paid what you have actually spent, so the Client is entitled to see the evidence. That is all "open book" means. The contract never uses the phrase, but clauses 52.2 and 52.3 produce the same result: you keep specified records, and the Project Manager (the person the Client appoints to run the contract day to day) can inspect them.

Options A and B are different. On a priced contract there is no standing right to see your accounts, although you may have to back up a compensation event quotation with evidence.

What changes for your team

Priced (A, B) Cost-based (C, D, E)
You are paid for Completed work at the Prices Defined Cost plus the Fee
Who sees your costs Nobody routinely The Project Manager and those acting for the Client
The key question Is it finished? Is it paid, proved and allowed?
People you need QS and measurement Cost accountant with ledger access
Overruns Yours Shared through the target, or the Client's on Option E

The records

Clause 52.2 expects:

  • accounts of Defined Cost payments, in practice a job ledger by section of the Schedule of Cost Components
  • proof the payments were made, such as bank statements or payment-run reports, each traceable to a ledger line
  • communications and assessments for subcontractor compensation events
  • anything else the Scope asks for, often timesheets, plant registers or tender records

Timesheets and similar are not named in the clause, but cost your records do not justify is Disallowed Cost, so in practice you need them.

A cost code structure that works

Mirror the Schedule of Cost Components rather than your internal management report. A fictional pumping station refurbishment might use:

Code Section
1.x People
2.x Equipment
3.x Plant and materials
4.x Subcontractors, by package
5.x Charges
6.x, 7.x Off-site manufacture and design
9.x Not Defined Cost (covered by the Fee), held separately

Keep non-recoverable items in that clearly marked code. A sample check will not trip over them, and your own accounts still reconcile.

Monthly reporting

Each month you should be able to show:

  1. Defined Cost paid to date, by section.
  2. Forecast Defined Cost before the next assessment date, with the working.
  3. Items you suspect may be disallowed.
  4. A forecast of total Defined Cost at Completion, updated at the interval in the Contract Data, with an explanation of changes (clause 20.4 in NEC3).
  5. A reconciliation to the last assessment.

NEC4 also lets you finalise Defined Cost for part of the works under clause 50.9, with timed review steps. Used well, it cuts the end-of-job load.

Where teams go wrong

  • Proof of payment held only at head office. Arrange access before the first inspection.
  • Allocations decided after the event. A year-end staff percentage is hard to defend.
  • Rebates and discounts living in another ledger. Clause 52.1 deducts them, so you need a way to find them.
  • No subcontract pricing information supplied. The NEC4 subcontract text asks for it at 26.4 unless agreed otherwise, so check the wording that applies to you.
  • Staff who see inspection as an intrusion. It is how you get paid. Explain that early.

In plain English

On a cost contract, if you cannot prove you paid it, you probably will not be paid for it. Set up the ledger to match the contract's cost headings from day one.

This guide is general information, not legal advice. Check it against your contract.