Can I be paid for materials and Plant on site or stored off site?
How NEC treats payment for Plant and Materials delivered to site or held off site: what to check in the Contract Data, ownership, and how to apply.
On this page
You have bought a large item or a stock of materials, it is on site or in a yard elsewhere, and you want it reflected in the next payment. Whether you can depends on the contract. This guide is written for a Contractor, and notes where a Subcontractor's position differs.
The short answer
Do not assume you will be paid for materials until they are installed. Check the Contract Data and the contract's provisions on Plant and Materials, in particular those covering Plant and Materials outside the Working Areas and the transfer of ownership. Then ask the Project Manager in writing, before you order, whether the item qualifies and what evidence is required.
What to do, step by step
- Read the provisions. Find the contract's provisions on Plant and Materials outside the Working Areas, and the clauses on who owns Plant and Materials. Check the Contract Data for any list of items that may be paid for, and any conditions. Check Z clauses as well.
- Identify the location. Items inside the Working Areas are treated differently from items outside them. Many contracts need written acceptance or specific conditions for items stored elsewhere.
- Ask before you buy. Write to the Project Manager (clause 13) describing the item, value, supplier, storage location and delivery date. Ask for confirmation of what will be paid and when.
- Meet the conditions. Typical conditions are identification and marking, insurance, a bond or guarantee, evidence of ownership passing, and access for inspection. The contract states which apply to you.
- Include it in your application. Show the item as a separate line, with its supporting records, in time for the next assessment date (clause 50).
- Check the assessment. If it is excluded, ask why and which condition is not met. See the Project Manager assessed my payment much lower than I expected.
- Check your supply chain. If you are a Contractor paying a supplier or Subcontractor, check their terms. Ownership and payment can be agreed differently down the chain.
Ownership matters
Payment for materials is closely linked to ownership. Under the core clauses (section 7), Plant and Materials outside the Working Areas stay where title is unless they are marked as for this contract, in which case the Contractor's title passes to the Client (clause 70.1). Marking is done under 71.1 and is available only where the contract lists the items for payment and you have prepared them as the Scope says. Items brought within the Working Areas pass to the Client on arrival (70.2), and title passes back to you only if they are removed with permission. If the Client has paid, you should not be using them elsewhere.
The clause only passes whatever title you hold. If a supplier's terms keep title until it is paid, there is nothing to pass, so a Client can pay for items and still not own them. Title and the risk of damage are separate matters, so a transfer of title does not move the risk. The risk of loss and the position if you or a supplier become insolvent depend on who holds title. This is a legal question. Take advice before you agree anything unusual, such as supplier retention of title terms.
Under Options C to F
On the cost-based Options (C, D, E and F), the test is what has been, or will be, paid before the next assessment date, so Plant and Materials count as Defined Cost once paid for under the contract's rules, net of recoverable discounts, and proof of payment is expected. Surplus beyond reasonable wastage is Disallowed Cost. On Options A and B, value comes only through completed activities or quantities, so buying early does not help cash flow unless the Activity Schedule or a Z clause provides for it. The same questions about location and ownership apply. See Defined Cost, Fee and Disallowed Cost.
What to record
- The order, supplier quotation and invoice.
- Delivery notes and goods received records.
- Photographs showing the items, labelling and storage.
- Insurance certificates and any bond or guarantee.
- Evidence of ownership transfer from the supplier.
- Written correspondence with the Project Manager about acceptance.
What not to do
- Do not buy large items on the strength of a conversation.
- Do not apply for items you have not yet paid for if the contract requires payment first.
- Do not store items off site without telling the Project Manager.
- Do not forget insurance. An uninsured item that is lost is your loss.
When to get help
Take legal advice on ownership and security for high-value items, especially where a supplier is retaining title. Talk to a planner when delivery dates affect the programme, because early delivery without a use date is weak evidence of value.
Example
A Contractor orders a large pump set. It will arrive in a supplier's yard in March and be installed in August. In January, the Contractor writes to the Project Manager with the supplier details, value, storage location, insurance and the proposed evidence of ownership. The Project Manager replies with the conditions that must be met, and the Contractor includes the pump in the March application with those documents attached.
Related guides
This guide is general information, not legal advice. Check it against your contract.