The Schedule of Cost Components: what you can and cannot charge on cost-based NEC

How the Schedule of Cost Components decides what counts as Defined Cost on NEC Options C, D and E, and what falls into your Fee instead.

Payment and cost3 min read

On this page
  1. Two tests every amount must pass
  2. How the schedule is laid out
  3. The sections that are easy to misread
  4. Six questions to ask of any cost
  5. Where people go wrong
  6. Related guides

On NEC Options C, D and E you are paid your actual cost plus a fee, but only for cost that the Schedule of Cost Components lists. Anything not on that list is not Defined Cost, and clause 52.1 treats it as already covered by your Fee. So the schedule decides what you recover and what you absorb. On Options A and B, a shorter version applies instead, the Short Schedule of Cost Components.

Defined Cost is the contract's term for the cost the Contractor has actually paid for the works, and the Fee is the percentage you tendered to cover what is left over. It is printed at the back of the contract, after the secondary Options. This guide is about the NEC4 Engineering and Construction Contract (ECC).

Two tests every amount must pass

  1. It sits in one component only. No double counting.
  2. It was incurred to Provide the Works. Costs belonging to another contract, or to your business generally, do not qualify.

The second catches people out. A regional manager's car might fit a listed item neatly, but if it serves five sites, you must show the share that belongs to this job and keep the allocation method on file.

How the schedule is laid out

In NEC4 there are eight sections: People (1, items 11 to 14), Equipment (2, items 21 to 28), Plant and Materials (3, items 31 and 32), Subcontractors (4, item 41), Charges and overheads (5, items 51 to 54), Manufacture and fabrication off site (6), Design off site (7) and Insurance deductions (8).

NEC3 is similar for the first three. The differences to know about:

  • Subcontractors are not a schedule section in NEC3. They sit in the Defined Cost definition itself.
  • Charges are section 4 in NEC3 (items 41 to 44) and include Working Areas overheads.
  • Off-site manufacture (5) and off-site design (6) each carry their own overheads percentage.
  • Insurance is section 7.

The NEC4 numbering above comes from the 2019 amended subcontract form, which follows the ECC layout. NEC has amended the schedule since it first appeared, so check the pages in your own copy.

The sections that are easy to misread

  • Manufacture and fabrication. Plant and Materials made wholly or partly for the works outside the Working Areas are priced at the people rates in Contract Data multiplied by the right time. A standard item you simply buy belongs under Plant and Materials.
  • Design off site. Priced the same way from Contract Data rates, plus listed travel between the designers' base and the Working Areas. Designers based in the Working Areas fall under People.
  • Insurance. This one is a deduction. The cost of events you must insure against is taken off, along with other sums insurers pay you, whether or not you actually bought the cover. If you spot a gap, take advice.

Six questions to ask of any cost

  1. Was it incurred to Provide the Works?
  2. Which single component does it fit?
  3. Does the component fix a rate or a basis (for instance open market rates)? Then use that rather than the invoice figure.
  4. Do discounts, rebates or recoverable tax bring it down (clause 52)?
  5. Does anything on the Disallowed Cost list remove it?
  6. Do your records prove it?

Failing the first two means the cost falls into the Fee. Failing the last two means it is removed as Disallowed Cost. You lose the money either way, but the argument and the evidence needed are different.

Where people go wrong

  • Applying it to Options A and B, which use the short schedule.
  • Tendering without filling in the Contract Data entries it depends on. A blank entry can cost you dearly later.
  • Carrying NEC3 habits across unchanged. Subcontractors joining the schedule, and the reworked overheads, are real differences.

This guide is general information, not legal advice. Check it against your contract.