Working under NEC on highways schemes: road space, utilities and sections
Practical NEC points for highways contractors: road space bookings, utility diversions, unknown services, weather, phased opening and term maintenance.
On this page
Highways work means building beside moving traffic, with road space that has to be booked and cables and pipes belonging to other parties. That makes when you can get in, and in what order you can work, the heart of the contract admin. The clauses are standard NEC4 Engineering and Construction Contract (ECC) ones, or the Term Service Contract for network maintenance. What changes is how much rides on the Scope (the document describing the work and its constraints) and the programme. Clients commonly amend the standard terms through Z clauses; this page cannot cover those, so read yours first.
In plain English
On road schemes, a lane closure is worth money. Whether losing one is your risk or the Client's depends on how the Scope and the Accepted Programme describe it, so check their wording before the first closure is lost.
Seven pressure points
- Traffic management and road space: who makes the booking, and who bears the risk if it is declined or shifted. It may be a Scope constraint or merely a programme date. Clauses: Scope, 31.2, 60.1(1).
- Access to the Site: the access date for each section. Late access only counts once both that date and the Accepted Programme date have gone by. Clauses 33.1 and 60.1(2).
- Utility diversions: whether utility companies are Others, and what times and conditions the Scope sets for them. Clauses 25.1 and 60.1(5).
- Unknown services and ground: measured against the Site Information, using the experienced contractor test. Clause 60.1(12).
- Weather-sensitive work: surfacing and earthworks, where you should ask whether the weather data in the contract matches the risk you priced. Clause 60.1(13).
- Phased opening: sections, Key Dates and what early use does. X5, 30.3, 35.2. See Key Dates and sectional completion.
- Delay damages: rates per section, and whether they fall when part of the road opens early. X7.1 and X7.3.
Road space is an access issue
A lane closure that has been booked is frequently the most valuable thing on the programme, so settle early how your contract classes it. Three positions are common:
- The Scope puts the booking, and working inside the notice rules, on you. A refusal is then probably your risk.
- The Client has to supply the closure. If it arrives late, you may have a compensation event.
- A later instruction cuts your permitted hours, which may be a change to the Scope under 60.1(1).
Each gives a different answer, and your Scope wording decides which you are in.
Utilities and Others
Utility diversions generate a large share of events on road schemes. Where the Scope or Accepted Programme dates a utility company's work and the company runs late, 60.1(5) may apply. In practice:
- Try to have diversion dates written into the Scope, and show them on the Accepted Programme regardless (31.2). See Others delaying your work and utilities found on site.
- Warn as soon as a utility's plans start to slip, not after the date has gone.
- Keep records of who attended and what was notified. Small slips are hard to prove afterwards.
Worked example
A fictional resurfacing job on a dual carriageway. The Accepted Programme shows a gas main diversion finishing in week 6, with surfacing to start in week 7. In week 5 the utility tells the contractor it will finish in week 10. The contractor warns immediately and the early warning meeting looks at re-sequencing the verge work. In week 7 the diversion is still incomplete, so the contractor notifies a compensation event under 60.1(5). Its quotation includes standing time, a revised sequence, and the effect on planned Completion and the sectional Key Date. The Project Manager (the person the Client appoints to run the contract day to day) can ask for alternative quotations.
Practical points for each side
- Contractor: record each night's progress, including closures lost and the reason. A shift can produce little yet cost a lot, and a daily log supports a better quotation.
- Project Manager: when a closure booking hinges on your answer, the standard reply period may be far too slow. Agree a faster route at an early warning meeting.
- Both: put road space booking dates on the programme, so that the Accepted Programme reflects the real constraint. See access dates and starting work.
Term maintenance on road networks
Network maintenance normally runs as a term arrangement rather than a one-off scheme. The Term Service Contract has no one Completion Date: work is ordered through Task Orders, each with its own dates, and compensation events are numbered differently. See the NEC term service contract and Task Orders explained.
Related guides
- Late access to site
- Utilities found on site
- Key Dates and sectional completion
- Bad weather and compensation events
This guide is general information, not legal advice. Check it against your contract.