The Bill of Quantities under NEC: what it does and does not do

How the NEC Bill of Quantities works under Options B and D, why it is not the Scope, and how to handle mistakes and measurement.

NEC Options and contract types3 min read

On this page
  1. What it does under each Option
  2. Rules by clause
  3. The method of measurement
  4. Correcting mistakes
  5. What 60.4 really does
  6. Measurement routine
  7. Common mistakes
  8. Related guides

The Bill of Quantities is the priced list of items, quantities and rates behind Options B and D. If you come from traditional contracts, the key difference is that nothing in the Bill forms part of the Scope. The Bill tells you how work is priced and measured. The Scope tells you what must be built. This guide uses NEC4 ECC with NEC3 numbers noted.

What it does under each Option

  • Option B. It drives payment. Monthly amounts come from measured work at your rates, plus the finished part of lump sum items. You measure regularly to get paid.
  • Option D. Monthly payment ignores it, because you are paid forecast Defined Cost plus the Fee. The remeasured Total of the Prices becomes the target for the final share. You measure regularly to forecast that share.

Rules by clause

Rule NEC4 NEC3
Bill content is not Scope or Site Information 56.1 55.1
A quantity change that alters unit cost may be an event 60.4 60.4
A quantity change that delays Completion or a Key Date is an event 60.5 60.5
Correcting a Bill mistake is an event 60.6 60.6
After an inconsistency is corrected, you are taken to have assumed the Bill right 60.7 60.7
Assessments are written as changes to the Bill 63.15 63.13

The method of measurement

Contract Data names the method for Options B and D and may state amendments. It matters twice: it decides how the Bill is written and what each item includes, and it sets the test for a mistake under 60.6, which is a departure from its rules on describing and dividing items. Civil and building methods differ, so if you use another method for part of the work, say so, and check the preamble does not quietly contradict it.

Correcting mistakes

Corrections go through the Project Manager, the person the Client appoints to run the contract day to day. A correction is a compensation event, and it can move the Prices up or down. Three invented cases:

  1. Missing item. The method requires a formwork item and the Bill lacks one. Adding it raises the Prices.
  2. Double counting. Excavation appears in two sections for one piece of work. Removing one lowers the Prices.
  3. Clashing documents. The Bill says 150 mm pipe, a drawing says 225 mm. Under 60.7 you are taken to have priced the Bill. If you priced 150 mm and 225 mm is instructed, the difference reaches you through the assessment.

What 60.4 really does

Ordinary variations in quantity do not reprice anything. All three of these must hold:

  1. the difference does not come from a Scope change;
  2. it changes your Defined Cost per unit;
  3. rate times final quantity exceeds 0.5% of the total Prices at the Contract Date.

If unit cost falls, the rate is reduced. Note that the threshold measures the item's final value, not the size of the change.

Measurement routine

  • Agree how and when measurement happens, who attends and how it is recorded.
  • Decide how lump sums such as preliminaries are proportioned.
  • Flag work with notified defects that would delay later work.
  • Reconcile billed against measured quantities as you go, and spot items heading for 60.4 or 60.5.
  • Update the Bill when events are implemented, in the 63.15 form.
  • Feed quantities into each payment, and on Option D into your share forecast.

Common mistakes

  • Reading a Bill description as the Scope. Where the two differ, the Bill creates no obligation, but the difference may point to a mistake to correct.
  • Treating every event as a Bill-rate exercise. Assessment is on Defined Cost; the Bill records the result.
  • Raising quantity effects only at the end. A delay under 60.5 happens during the job, so the normal notification time limits apply.

This guide is general information, not legal advice. Check it against your contract.