How to build an NEC Activity Schedule that gets you paid on time

How to build and maintain an NEC Activity Schedule for Options A and C: sizing activities, tying them to the programme, and avoiding disputes.

NEC Options and contract types3 min read

On this page
  1. What the contract says
  2. Building one
  3. Fixing a weak line
  4. Using it during the job
  5. Common errors
  6. Related guides

On Options A and C you write the Activity Schedule yourself: a priced breakdown of the job where every line is a lump sum and the lines add up to the Prices. It controls what you are paid, and when, on Option A. On Option C it merely fixes the target. A well-built one makes payment, programme updates and compensation events simple. A poor one causes argument at every assessment. This guide uses NEC4 ECC and notes NEC3 numbers.

What the contract says

Rule NEC4 NEC3
Link activities to operations on each programme you submit 31.4 31.4
Its content carries no Scope or Site Information weight 55.1 (A), 55.2 (C) 54.1
You correct it if activities do not match the Scope 55.1 (A) no equivalent
When you must submit a revision 55.3 (A) 54.2
Reasons a revision may be refused 55.4 (A) 54.3
Changed Prices for compensation events are recorded in it 63.14 63.12

The point in 55.1 is worth remembering. If the schedule misses work the Scope requires, you must still do it, with no extra payment. And nothing listed in the schedule adds to the Scope.

Building one

  1. Begin with the programme, not the estimate. Group programme operations into activities and the clause 31.4 link takes care of itself.
  2. Say what finished means. "Foundations" is vague. "Pile caps 1 to 12 cast and backfilled" is something an inspector can verify.
  3. Size for cash flow. On Option A an unfinished activity earns nothing. Many teams aim to finish activities within one or two assessment intervals. That is practice, not a contract rule.
  4. Place preliminaries on purpose. Set-up and removal can be their own lines. Running costs can be split into a monthly time-related activity.
  5. Spread allowances sensibly. The total must carry the whole price, but a very front-loaded schedule invites challenge.
  6. Group with care. Activities can be grouped and paid when the whole group finishes. On termination, grouping is ignored (93.3).

Fixing a weak line

Take a fictional pumping station fit-out with four-weekly assessments. A single line "Mechanical and electrical: £620,000" waits maybe twenty weeks for payment, puts the whole sum at risk if one area is disputed, and is one bar over many operations. Break it up: first fix floor by floor, the plant room, second fix floor by floor, then commissioning. Each pays within roughly four to eight weeks, a dispute touches only its own line, and each links to specific operations.

Using it during the job

  • Option A assessments: keep a dated list of finished activities, agreed or signed off, with any defect that would delay following work noted.
  • Method changes: submit a revision under 55.3. The Project Manager may refuse only for reasons in 55.4: it does not relate to the Accepted Programme, changed Prices are not reasonably spread across remaining work, or the total has moved.
  • Compensation events: change the schedule under 63.14, by adding an activity or altering existing ones. Pick one convention and keep to it.
  • Option C: keep it current though it does not drive monthly payment, because it underpins the target and its total must be right at Completion.

Common errors

  1. Using it as a summary of your estimate. Trade-based lines make the 31.4 link hard to show.
  2. Moving money between activities without a revision. That is not allowed by the contract and an audit will find it.
  3. Believing its wording shapes your duties. Under 55.1 it neither adds to nor removes from the Scope.
  4. Scaling lump sums to price compensation events. Assessment rests on Defined Cost unless both sides agree otherwise.
  5. Letting the programme move while the schedule stays still.

This guide is general information, not legal advice. Check it against your contract.