Which NEC contract form is this, and why was it chosen?

A practical guide to the NEC family of contracts: what each form is for, how to tell if the right one has been used, and what to check.

NEC Options and contract types4 min read

On this page
  1. The five questions
  2. Typical matches
  3. Two invented cases
  4. Grey areas
  5. Checks before you commit
  6. Related guides

Most contractors are handed an NEC form rather than choosing one, but it still pays to know whether it fits the work. The right form depends on five things: the thing being bought, the shape of the work in time, the level of risk, your place in the supply chain, and the way cost risk is to be shared. A mismatch is hard to repair once tenders are in.

The five questions

  1. What is being bought? Physical work points to the Engineering and Construction Contract (ECC) family. Advice or design points to the professional service forms. A continuing service points to the term or facilities management forms. Goods point to the supply forms.
  2. One defined job, or work called off over time? The ECC suits work with one finishing date. If the work recurs and is partly unknown, a term contract fits, with each piece ordered separately.
  3. Is it simple and low risk? Then a short form may do. What matters is how simple the work is and how little management it needs. No NEC form has a price ceiling.
  4. Is the client letting part of its own contract? If a main contractor is passing work down, a subcontract form is needed.
  5. How is cost risk shared? The answer picks the main Option, on forms that offer one.

Typical matches

Each pairing is a starting point to read the form against, not a rule.

Physical works

  • A new road, building or plant, whoever designs it: the ECC.
  • A small repair with a clear scope and few unknowns: the short contract (ECSC).
  • A main contractor letting out groundworks: the subcontract (ECS), or the short subcontract (ECSS) for a simple package.
  • One firm building an asset and then running it for years: Design Build Operate (DBO).
  • Client, designers and builders all sharing risk over a programme of work: the Alliance Contract (ALC).

Advice and design

  • A lead designer on a complex scheme: the Professional Service Contract (PSC).
  • A one-off survey or brief advice: the short professional contract (PSSC).
  • Passing part of a consultancy to another firm: the Professional Service Subcontract (PSS).

Continuing services

  • Five years of drainage maintenance: the Term Service Contract (TSC).
  • Simple grounds care at a single site: the short term contract (TSSC).
  • Estate-wide cleaning, security and building services: the Facilities Management Contract (FMC).

Goods and call-offs

  • Buying and installing a large transformer: the Supply Contract (SC).
  • Regular deliveries of a standard product: the Short Supply Contract (SSC), using batch orders.
  • A pool of suppliers standing by for packages nobody has defined yet: a Framework Contract (FC), with orders placed under other forms.

Two invented cases

A school extension. A two-classroom extension on an occupied site looks small enough for the short form. But it has phased access, a live kitchen next door and handover dates for each school holiday. Key Dates, the contract's fixed milestone dates, do not exist in the short form, so the ECC is the sounder choice despite the size.

Regional pipe repairs. A water company wants burst repairs across three years without knowing where they will be. One ECC per repair would mean endless tendering. The TSC fits better: a price list agreed once, then an order for each task. If a big planned mains renewal appears, it may deserve its own ECC.

Grey areas

  • Work mixed with service. Decide the main purpose. Two separate contracts can be better if different firms do each phase.
  • Design and build. The ECC already covers contractor design. A professional service form is not needed for that, though your own designer's appointment under you may be a PSS.
  • Supply plus fitting. If there is substantial site work, the ECC may suit better than the supply form. Take advice on whether the Construction Act applies.
  • The short-form attraction. It saves effort only while the job stays simple.

Checks before you commit

  • Is the edition the same on your main contract and subcontracts, or is the mix deliberate?
  • Is it clear who will fill the manager role (Project, Service or Supply Manager, depending on the form), and are they ready for it?
  • Who completes which part of the data sheets?
  • Which secondary Options are needed, and does the form allow them? Short forms have none.
  • Has a contracts adviser looked at anything unusual?

This guide is general information, not legal advice. Check it against your contract.

Was this useful?