The NEC4 subcontract (ECS): what changes when you are the subcontractor

How the NEC4 Engineering and Construction Subcontract differs from the main contract: who is who, shorter periods, and how it ties to the job above.

NEC Options and contract types3 min read

On this page
  1. Who is who
  2. Where your subcontract reaches upwards
  3. Periods you must diarise
  4. Main Options
  5. Your checklist
  6. If you are the main contractor issuing it
  7. Related guides

If you are a subcontractor on an NEC4 job, your paperwork is probably the Engineering and Construction Subcontract (ECS). It is the form a main contractor uses to let part of its works. It copies the main contract's clause numbering, so it feels familiar to anyone who has read the main contract, but the people are different and several time periods are not the same. Both points can cost you money if you run on memory.

Who is who

Your subcontract replaces the main contract's roles with a new set of names.

  • The main contractor takes over both the Client's and the Project Manager's places. It is the person you notify, the one who replies, and the one who pays you.
  • You become "the Contractor" in the sense the main contract uses, but the form calls you the Subcontractor.
  • The project-specific numbers sheet is the Subcontract Data, and the specification of your work is the Subcontract Scope.
  • Anyone you sub-let to becomes a Subsubcontractor.

You have no contract with the real Client, so every notice goes to the main contractor, whoever you actually talk to on site. The Subcontract Data still names the main contract's Client, Project Manager, Supervisor and Adjudicator, so you know who sits above you.

Where your subcontract reaches upwards

  • Early warning meetings. Under 15.2 the main contractor can require you to join a main contract meeting where the matter affects your work.
  • Disputes. If the same issue is being disputed at both levels, you can be brought into the main contract adjudication so one Adjudicator decides both.
  • Termination. The main contractor has a listed reason to end your subcontract if its own duty to provide the works has been terminated (91.9, reason R23).
  • Design. Rights to use your design extend to the Client as well, unless your Subcontract Scope says otherwise.

Periods you must diarise

These are the unamended defaults. Amendments often change them, so read your own Subcontract Data.

What Main contract Your subcontract
Notify a compensation event 8 weeks 7 weeks
Quotation due 3 weeks 2 weeks
Main contractor's reply to your quotation 2 weeks 4 weeks
Reply to your programme 2 weeks 3 weeks
Payment after the assessment date 3 weeks 4 weeks, or as the Subcontract Data states

The gaps are there so the main contractor can pass things up and down the chain. For you, the key shift is the seven-week notification period, not the eight you may remember. See time bars for subcontractors.

Main Options

The ECS has Options A, B, C, D and E. There is no management form, so no Option F equivalent. Your subcontract need not use the main contract's Option: a main contractor on a target contract may let you a package on fixed lump sums. The usual secondary Option letters are available, with some differences. X11, for instance, covers termination by the main contractor.

Your checklist

  1. Diarise seven weeks to notify, not eight.
  2. Send every notice to the main contractor, regardless of who you deal with day to day.
  3. Ask for the parts of the main contract that restrict your work, such as access limits.
  4. Read how NEC defines a Subcontractor before you sub-let anything yourself.
  5. Check that your Subcontract Scope and completion date fit the main contractor's programme.
  6. Treat any Z clause as a signal: ask what risk it moves to you.

If you are the main contractor issuing it

Confirm the main contract is NEC4 (references may not work otherwise), fill in the main contract details, flow down the main Scope including constraints, and decide who in your team acts as "the Contractor" with time to reply. Keep any Z clause narrow.

Under NEC3 the ECS exists with older terms and different periods, so read that form directly.

This guide is general information, not legal advice. Check it against your contract.