Pay less notices under NEC: deadlines, content and who can send one
What a pay less notice must say, the seven-day deadline under Option Y(UK)2, and what happens to the payer who misses it.
On this page
A pay less notice is the formal warning a payer must give before paying less than the amount certified. Under Option Y(UK)2, it has to reach the other side no later than seven days before the final date for payment. If it does not, the certified amount generally has to be paid, even where the certificate is wrong.
For a contractor or subcontractor this cuts both ways: it protects you when a Client or main contractor tries to knock money off late, and it binds you if a certificate shows you owe something.
The rule is in clause Y2.3 in both NEC3 and NEC4. Option Y(UK)2 is the secondary Option that writes the Construction Act's payment rules into the contract.
The essentials
| Question | Answer |
|---|---|
| Who gives it? | The paying party, whichever side that is |
| What is it measured against? | The sum in the Project Manager's certificate (the Project Manager is the person the Client appoints to run the contract day to day) |
| When? | At least seven days before the final date for payment |
| Content? | The sum now considered due, and how it was calculated |
| If none is given? | The certified sum should be paid |
On the standard periods, the assessment date is day 0, the final date for payment is day 21, so the last day for a notice is day 14. A different payment period in your Contract Data moves all of these.
The notice replaces the figure
Say a certificate is for £100,000 and the payer spots a £20,000 overvaluation on day 12. The notice must not say "we will deduct £20,000". It must say the sum considered due is £80,000 and show how that comes about. The payer then pays the figure in the notice. Had the same discovery come on day 15, it would be too late for this cycle: the full £100,000 would be paid and the error put right through the Project Manager's correction in the next certificate under clause 50.6.

What the notice should contain
- The contract name and reference, and which certificate it relates to.
- A plain statement that it is a notice of intention to pay less under Y2.3.
- The certified sum and the final date for payment.
- The sum now considered due.
- The basis: each reason with its amount.
- The sender's name and role, showing authority to act.
- The date, and proof of when it was received.
Who can send it
The clause refers to a party. A Project Manager does not automatically hold that authority, so if the Client wants its Project Manager or another consultant to send notices, set that out in writing early. Check the contract's communication rules as well: a notice sent to the wrong address or in the wrong form can be challenged.
Common mistakes
- Treating the Project Manager's later correction as if it were a notice. It belongs to the next cycle.
- Giving a bare number with no basis.
- Counting days loosely. Under the NEC4 subcontract text, Y2.1 excludes Christmas Day, Good Friday and bank holidays from the count. NEC3 follows the Act's own method. Check your wording before relying on a tight date.
- Believing a dispute stops the clock. It does not.
- Serving a notice too early for a problem that has not yet arisen. It can only rely on what is known.
Related rights
Where the payer does not pay, the Act lets the payee suspend work. Under Y(UK)2 a proper suspension is a compensation event, at Y2.5 in NEC4 and Y2.4 in NEC3. Take advice before suspending, because there are notice requirements. NEC4 also adds Y2.4 on certified sums unpaid at termination. And without Y(UK)2 the Act can still apply, with the statutory Scheme filling any gap and possibly changing the periods.
A valid notice only decides what is paid now. Either side can still take the true value to adjudication.
In plain English
To pay less than the certificate, you must tell the other side the new figure and why, a week before payment is due. Miss that, and you pay in full and argue later.
Related guides
- Y(UK)2: the Construction Act option
- The Client missed the pay less notice
- The NEC payment timeline
- Adjudication under NEC
This guide is general information, not legal advice. Check it against your contract.