The Project Manager will not certify Completion
What to do if the works are finished but the Project Manager will not certify Completion: check the definition, record the facts, ask in writing, escalate.
On this page
You believe the works are complete, but the Project Manager has not certified Completion. Delay costs money: delay damages may be running if Option X7 applies, the halving of retention under Option X16 waits for the date, and the Defects Date and the correction periods for earlier-notified Defects all count from it. This guide is written for a Contractor. A Subcontractor in the same position should read it against the subcontract and speak to the Contractor.
The short answer
Check what your contract says Completion means, then ask the Project Manager in writing to certify, with evidence that the definition is met. Completion is not a matter of opinion alone: the contract defines it, and the Project Manager must act as the contract says. Get your case on the record promptly so the date is not allowed to drift.
What to do, step by step
- Read the definition. Find the definition of Completion in the contract and the Scope (Works Information in NEC3). Completion means the Contractor has done the work the Scope says is to be done by the Completion Date, and has corrected notified Defects that would stop the Client using the works or Others doing their work (clause 11.2). If the Scope does not say what work is needed by the Completion Date, the test falls back on what the Client needs to use the works and what Others need to do theirs. Unfinished work the Scope lists for that date holds Completion up even if it is small, while a minor notified Defect that does not prevent use does not. Under clause 30.2 the Project Manager decides the date and certifies it within one week of that date. Check the exact wording in your contract and Z clauses.
- Check any Key Dates and sections. If there are sectional completion dates or Key Dates, work out which apply.
- Compare the works with the definition. Walk the site with a checklist. Separate genuine omissions from minor matters. Check outstanding Defects against the Defects clauses (about clauses 40 to 46). See defects under NEC.
- Ask the Project Manager in writing. Using clause 13 communications, state that in your view the definition is met, give the date, list the evidence, and ask the Project Manager to certify Completion by a stated date, mentioning the one-week period in clause 30.2. Ask for reasons in writing if the answer is no.
- Request a joint inspection. Offer a date for the Project Manager and Supervisor to inspect. Invite them to list anything they say is outstanding.
- Close out the list. If the Project Manager lists items, deal with them quickly and report back. If you disagree with an item, say why.
- Check the programme and compensation events. If the Completion Date should have moved because of compensation events, make sure those are notified, quoted and implemented. See compensation events in plain English.
- Escalate. Involve the commercial managers. If the position does not move, take legal advice and consider the dispute resolution Option in your contract. Under Option W2 you can go to adjudication at any time, but under W1 a four-week limit runs from becoming aware of the decision you dispute. See adjudication under NEC.
For what follows certification, see completion, take over and the defects date.
What to record
- The definition of Completion and your analysis against it.
- Dated photographs and test records.
- The Supervisor's tests, inspections and any Defect notices.
- Your letter requesting certification, with date sent.
- The Project Manager's response and reasons.
- Any use the Client has made of the works, and when.
What not to do
- Do not announce Completion unilaterally and stand down site.
- Do not rely on a verbal "we are nearly there".
- Do not leave small outstanding items open for weeks. They give the Project Manager reasons to refuse.
- Do not forget to keep recording. If the date is later found to be earlier, the evidence will matter.
- Do not mix a Completion claim with unrelated payment complaints in one letter.
When to get help
If delay damages are being deducted, if the Client is using the works without certifying, or if the amount at stake is large, take legal advice. A planner can help where the date turns on the Accepted Programme and the effect of events on the Completion Date. See delay analysis basics.
Example
A Contractor finishes the pumping station on the planned date. Two minor snagging items remain and the Project Manager says Completion is not certified. The Contractor checks the definition, finds the items do not prevent the Client using the works, writes with photographs and test records requesting certification within a stated number of days, and invites a joint walk-round. The Project Manager responds with a list of five items, three of which the Contractor closes the same week.
Related guides
This guide is general information, not legal advice. Check it against your contract.