How tests and inspections work under NEC
What the NEC test and inspection clause covers, the notice you must give, the three compensation events linked to testing and who pays for a repeat test.
On this page
Testing under NEC is short on detail and long on consequences. Clause 41 of the NEC4 ECC (40 in NEC3) covers only the tests and inspections demanded by the Scope (the document setting out what the Contractor must deliver, called Works Information in NEC3) or by law. Warn the other side before testing, share the results afterwards, and if a test exposes a Defect (work that does not meet the Scope), put it right and test again. The practical question is who pays when something fails.
The clause at a glance
| Topic | NEC4 ECC | NEC3 ECC |
|---|---|---|
| Only tests the Scope or the law require | 41.1 | 40.1 |
| Materials, facilities and samples as the Scope states | 41.2 | 40.2 |
| Notice before, results after, right to watch | 41.3 | 40.3 |
| Defect found: correct, then repeat the test | 41.4 | 40.4 |
| Supervisor causes no unnecessary delay | 41.5 | 40.5 |
| Cost of a repeat test charged to the Contractor | 41.6 | 40.6 |
| Items tested before delivery | 42.1 | 41.1 |
In plain English
Give the Supervisor (the person who checks quality for the Client) enough warning to attend. If a test fails because your work is defective, you pay the Client's cost of the retest. If the Supervisor or the Client causes needless delay, you may have a compensation event.
The notice that catches people out
Tell the Supervisor early enough that the test can be set up and done before the next trade hides the work. The clause gives no number of days, so the Scope should. The risk shows up if you cover work untested and the Supervisor then orders a search. A search that finds no Defect is usually a compensation event in your favour, but not when it only arose because you gave too little notice. Think of a screed laid over pipework before the pressure test was witnessed.
Three compensation events to know
- 60.1(10): the Supervisor orders a search and finds nothing wrong.
- 60.1(11): the Supervisor's own test or inspection holds you up more than it needed to.
- 60.1(16): the Client fails to supply what the Scope promised for testing: materials, facilities or samples.
Notice the word "unnecessary" in the second one. A test that takes its fair time is not an event, even if it breaks your sequence. Keep a note of when you asked for attendance and when the Supervisor turned up, because the argument will turn on those two dates.
Who pays for a repeat test
When a Defect leads to a retest, the Project Manager assesses what the repeat cost the Client and you pay it (41.6). That covers items such as the Supervisor's team or a laboratory the Client engages. Your own cost of putting right and retesting is dealt with through your main Option.
Payment tied to a test
Some payments are conditional on a test being passed. If the Supervisor never carries that test out and you are not to blame, the payment still becomes due, though only after the defects date and the last defect correction period have both gone by. That could mean a long wait, so chase the missing test in writing rather than counting on this fallback.
Testing before delivery
If the Scope requires Plant and Materials to pass tests before delivery, keep them off the Working Areas until you hear they have passed. Show that confirmation as its own dated step in the programme.
What to put in the Scope
- A schedule of each test and inspection, and who carries it out.
- The notice period for each hold point.
- Who provides materials, facilities and samples.
- Pass criteria that can be measured.
- The list of items tested off site, and the place.
Example
A fictional footbridge deck has a cube test that fails. The Contractor recasts the affected pour. The Client's laboratory charges £900 for the retest and the Project Manager assesses that sum against the Contractor. Breaking out and recasting is a separate cost the Contractor carries on a fixed-price Option.
Related guides
This guide is general information, not legal advice. Check it against your contract.
