Work is finished but compensation events are still open
How to close out unresolved compensation events after Completion: the cut-offs, who must act next, and how to avoid losing them in the final account.
On this page
You have reached Completion, but several compensation events have never been agreed. People are leaving the project, and someone has said it will all be dealt with in the final account.
The short answer
You can still settle them, because reaching Completion does not close the compensation event process. The hard deadlines arrive later. Clause 61.7 sets a cut-off after which no new event can be notified. In NEC4 the final assessment comes within four weeks of the Defects Certificate, and it does not wait for your open events. So list each one, find where it has stalled, and push the next step.
What to do, step by step
- Find the two dates your plan hangs on: the defects date and, once issued, the Defects Certificate date.
- List every open event, including any you know about but never notified. Remember the eight weeks in clause 61.3.
- Slot each event into the stage table further down, noting whose turn it is.
- Use the failure notices. If the Project Manager has gone quiet, notify the failure. That starts the further period.
- Agree a closure programme with the Project Manager and settle the biggest first.
- Protect yourself on the final assessment. If you disagree with it, you may have just four weeks from its issue to start the dispute route.
| Where it has stalled | Who acts | Period | If nothing happens |
|---|---|---|---|
| You notified, no reply | Project Manager | 1 week (61.4) | You notify the failure; after 2 more weeks it counts as an event and quotations as instructed |
| Quotation instructed, not sent | You | 3 weeks (62.3) | Project Manager may assess (64.1) |
| Quotation sent, no reply | Project Manager | 2 weeks (62.3) | You notify the failure; after 2 more weeks it is treated as accepted (62.6) |
| Project Manager said it would assess, nothing issued | Project Manager | The quotation period (64.3) | You notify the failure; treated acceptance of your quotation can follow (64.4) |
| Event known, never notified | You | 8 weeks (61.3) | Prices and dates don't change for your late event |
The eight-week limit does not catch an event arising from the Project Manager's instruction, notification or certificate, or a changed decision. These can be notified late, up to the final cut-off.
What to record
- The date of every notification, quotation, reply and failure notice
- A single list of open events with stage, owner and next date
- Records of who worked where, before staff leave
- Dated copies of everything sent
What not to do
- Do not assume silence means acceptance. Treated acceptance needs your failure notice and then the further two weeks.
- Do not accept the line that everything goes into the final account. The periods still apply. A batch settlement is fine if it is recorded event by event.
- Do not forget the cut-off: for NEC3 ECC it is the defects date, for the NEC4 subcontract it is the Defects Certificate, and for NEC4 ECC you should check the wording in your own contract. It bars a new notification, not an event already notified.
- Do not under-price. An implemented event stands (clause 66.3), and pricing after the work is done still rests on actual cost to the dividing date and forecast after it.
When to get help
A commercial manager should lead, because the position differs by main Option. Under A and B, an event still unimplemented leaves the Prices unchanged. Under C and D events move the target and so the final share. Under E the money effect is small and it matters mainly for the Completion Date.
Example
You sent a quotation on 3 March and the two weeks passed. On 20 March you notify the failure in writing, stating that clause 62.6 applies and offering a meeting on the full open list. If the Project Manager is still silent after two further weeks, your quotation counts as accepted.
Related guides
- Time bars explained
- Pricing a compensation event after the work is done
- Disagreeing with the final assessment
- Failure to reply and treated acceptance
This guide is general information, not legal advice. Check it against your contract.