Your request for information has gone unanswered: what to do under NEC

How to turn an ignored RFI into something the NEC contract recognises, protect your programme, and decide whether a late answer is worth a compensation event.

Communications and recordsScenario3 min read

On this page
  1. The short answer
  2. What to do, step by step
  3. Which route fits your question
  4. What to record
  5. What not to do
  6. When to get help
  7. Example
  8. Related guides

You sent a request for information, the site is getting close to the affected work, and nobody has replied. Whether the silence helps you under the contract depends on what you actually asked.

The short answer

"RFI" is not an NEC term, and the contract does not care what your form is called. It cares what the communication asks for. If the contract requires a reply, the Project Manager (the person the Client appoints to run the contract day to day) must answer within the period for reply in Contract Data (clause 13.3), and a missed reply can be a compensation event, meaning an event that can change your price or dates. So first work out which route your question falls under, resend it in those terms, and protect your programme with an early warning.

What to do, step by step

  1. Find the due date. Date the question was received plus the period for reply. Check that nobody agreed an extension before that date (13.5).
  2. Give an early warning now if the delay could matter. Name the operation that is waiting and the last date an answer can arrive without harm.
  3. Resend the question in contract terms. Pick the route from the list below and send it to the Project Manager.
  4. Notify a compensation event if there is a real effect. A missed reply falls under 60.1(6). No exemption from the time bar applies, so the eight weeks in 61.3 start when you realised the reply was missed.
  5. Keep working sensibly. Resequence where you can, and note why you did or did not.

Which route fits your question

What you were really asking Route
Two documents contradict each other Notify it under 17.1 and ask the Project Manager to rule; the ruling may itself change the Scope
A missing drawing or item the Client owes you Compare with the date on the Accepted Programme (60.1(3)); the period for reply is not the test
Information from a separate designer or other party Possibly 60.1(5), if the times shown were missed; your programme should show when you need it
Acceptance of a design or proposal A submission for acceptance under 13.4, where a reply is plainly required
How to build something Probably no contract route; the method is your job

What to record

  • The RFI, its date, and proof of receipt.
  • The date a reply was due and any agreed extension.
  • The activity waiting on the answer, with its planned start.
  • Every chase, and any answer, however informal.
  • The effect on the Accepted Programme, once you can see it.

What not to do

  • Do not assume a heading on a form creates a duty to reply.
  • Do not send hundreds of open items at once. Rank them and send the few that hold up work, with the dates they matter by.
  • Do not wait to see whether the late reply "turns out" to cost anything before diarying the eight weeks.
  • Do not claim if the answer was already in the documents: the delay was then yours.
  • Do not leave the question too late. Asking on day one of a two-week period, for work starting in a few days, makes nobody late but you.

When to get help

Involve your commercial manager if a critical activity is waiting, and a planner to show the effect on Completion. A late reply on an activity with plenty of float may be worth nothing: under 61.4 an event with no effect changes nothing.

Example

A drainage subcontractor's RFI 12, sent on 3 March, points out that the pipe levels schedule and the layout drawing disagree. It is resent on 5 March under clause 17.1: "The pipe gang starts on 31 March. Without an answer by 17 March we expect to lose time. We are giving an early warning separately." No answer arrives. On 20 March the contractor notifies the missed reply and records the lost days.

This guide is general information, not legal advice. Check it against your contract.